,Question 1 Which approach for constructing a WBS uses a similar project’s
WBS as a starting point?
a) mind-mapping
b) bottom-up
c) top-down
d) analogy
Question 2 The table that lists requirements, their various attributes, and the
status of the requirements to ensure that all are addressed is referred to as
_______.
a) Gantt chart
b) requirements traceability matrix
c) state transition table
d) entity-attribute-value model
Question 3 Which project management knowledge area ensures that the
project will satisfy the stated or implied needs for which it was undertaken?
a) Project time management
b) Project risk management
c) Project quality management
d) Project cost management
Question 4 The organization recognizes that a new project exists and
completes a project charter during which processes for a new project?
a) opening
b) initiating
c) planning
d) controlling
Question 5 In project schedule management, what is the next step after
defining project activities?
a) planning schedule management
b) controlling the schedule
c) determining their dependencies
, d) estimating activity duration
Question 6 What document used to coordinate all project planning documents
and help guide a project’s execution and control?
a) project management plan
b) statement of work
c) scope statement
d) business case
Question 7 Which statement best describes scope?
a) work involved in creating the products and the processes used to create them
b) each level of work that is outlined in a work breakdown structure
c) end product created as part of a project that is delivered to the client
d) tasks that are decomposed into smaller tasks in a work breakdown structure
Question 8 According to Thamhain and Wilemon, what is the ability to
improve a worker’s position?
a) penalty
b) promotion
c) assignment
d) expertise
Question 9 What are the bottom four needs in Maslow’s structure are referred
to as?
a) self-actualization
b) deficiency
c) safety
d) growth
Question 10 Which software development approach allows developers to use
a model to generate functional requirement and physical design specifications
concurrently?
a) Prototyping approach
b) incremental approach
c) RAD approach
d) Waterfall approach
, Question 11 The main outputs of which process are team performance
assessments, change requests, and updates to several documents?
a) managing the project team
b) acquiring the project team
c) human resource planning
d) developing the project team
QThe project cost that can be recovered by making fixed charges on the
development departments, or by an additional percentage charge on direct
staff employment costs is known as ____.
a.
Staff cost
b.
Overhead cost
c.
Usage cost
d.
Staff extra costuestion 12 Which technique is used for making cost and
schedule trade-offs to obtain the greatest amount of schedule compression
for the least incremental cost?
a) crashing
b) dependency
c) feeding buffers
d) breakdown structure
100%
Crystal Indigo!
Crystal Indigo!
Providing all solutions you need anytime
+27 76 626 8187
,Question 1 Which approach for constructing a WBS uses a similar project’s
WBS as a starting point?
a) mind-mapping
b) bottom-up
c) top-down
d) analogy
Question 2 The table that lists requirements, their various attributes, and the
status of the requirements to ensure that all are addressed is referred to as
_______.
a) Gantt chart
b) requirements traceability matrix
c) state transition table
d) entity-attribute-value model
Question 3 Which project management knowledge area ensures that the
project will satisfy the stated or implied needs for which it was undertaken?
a) Project time management
b) Project risk management
c) Project quality management
d) Project cost management
Question 4 The organization recognizes that a new project exists and
completes a project charter during which processes for a new project?
a) opening
b) initiating
c) planning
d) controlling
Question 5 In project schedule management, what is the next step after
defining project activities?
a) planning schedule management
b) controlling the schedule
c) determining their dependencies
, d) estimating activity duration
Question 6 What document used to coordinate all project planning documents
and help guide a project’s execution and control?
a) project management plan
b) statement of work
c) scope statement
d) business case
Question 7 Which statement best describes scope?
a) work involved in creating the products and the processes used to create them
b) each level of work that is outlined in a work breakdown structure
c) end product created as part of a project that is delivered to the client
d) tasks that are decomposed into smaller tasks in a work breakdown structure
Question 8 According to Thamhain and Wilemon, what is the ability to
improve a worker’s position?
a) penalty
b) promotion
c) assignment
d) expertise
Question 9 What are the bottom four needs in Maslow’s structure are referred
to as?
a) self-actualization
b) deficiency
c) safety
d) growth
Question 10 Which software development approach allows developers to use
a model to generate functional requirement and physical design specifications
concurrently?
a) Prototyping approach
b) incremental approach
c) RAD approach
d) Waterfall approach
, Question 11 The main outputs of which process are team performance
assessments, change requests, and updates to several documents?
a) managing the project team
b) acquiring the project team
c) human resource planning
d) developing the project team
QThe project cost that can be recovered by making fixed charges on the
development departments, or by an additional percentage charge on direct
staff employment costs is known as ____.
a.
Staff cost
b.
Overhead cost
c.
Usage cost
d.
Staff extra costuestion 12 Which technique is used for making cost and
schedule trade-offs to obtain the greatest amount of schedule compression
for the least incremental cost?
a) crashing
b) dependency
c) feeding buffers
d) breakdown structure