100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Contemporary Project Management, Kloppenborg - Exam Preparation Test Bank (Downloadable Doc)

Rating
-
Sold
-
Pages
203
Grade
A+
Uploaded on
20-05-2022
Written in
2021/2022

Description: Test Bank for Contemporary Project Management, Kloppenborg, 1e prepares you efficiently for your upcoming exams. It contains practice test questions tailored for your textbook. Contemporary Project Management, Kloppenborg, 1e Test bank allow you to access quizzes and multiple choice questions written specifically for your course. The test bank will most likely cover the entire textbook. Thus, you will get exams for each chapter in the book. You can still take advatange of the test bank even though you are using newer or older edition of the book. Simply because the textbook content will not significantly change in ne editions. In fact, some test banks remain identical for all editions. Disclaimer: We take copyright seriously. While we do our best to adhere to all IP laws mistakes sometimes happen. Therefore, if you believe the document contains infringed material, please get in touch with us and provide your electronic signature. and upon verification the doc will be deleted.

Show more Read less
Institution
Course











Whoops! We can’t load your doc right now. Try again or contact support.

Connected book

Written for

Institution
Course

Document information

Uploaded on
May 20, 2022
Number of pages
203
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Chapter 1 - Introduction to Project Management




TRUE/FALSE



1. A project is a temporary endeavor undertaken to create a unique product, service or result.


ANS: T DIF: Easy REF: 1.1 OBJ: Define a project



2. A project is a lasting endeavor undertaken to maintain a reliable product or service.


ANS: F DIF: Easy REF: 1.1 OBJ: Define a project



3. Most projects are conducted with constraints on the amount of time and funding available to the
project manager.


ANS: T DIF: Average REF: 1.1 OBJ: Define a project



4. Project plans and goals usually become more specific as early work is completed.


ANS: T DIF: Challenging REF: 1.1 OBJ: Define a project



5. Projects consist of the ongoing work needed to ensure the organization continues to function
effectively.


ANS: F DIF: Average REF: 1.3 OBJ: Define a project



6. Customers may need to sacrifice expectations related to cost or schedule in order to realize their
expectations for scope or quality.

, ANS: T DIF: Challenging REF: 1.3 OBJ: Define a project



7. The most critical measures of project success are completing the project on schedule and on
budget.


ANS: F DIF: Challenging REF: 1.4 OBJ: Measures of success



8. Some projects are considered successful if they reap business benefits like increased profitability,
even if completed late or over budget.


ANS: T DIF: Challenging REF: 1.4 OBJ: Measures of success



9. In reality, many projects are fully successful in some ways, but less successful in others.


ANS: T DIF: Average REF: 1.4 OBJ: Measures of success



10. Integration management relies upon tools such as project charters, project plans and change
control to unify and coordinate the activities associated with the project management knowledge
areas.


ANS: T DIF: Average REF: 1.4 OBJ: Issues for knowledge
areas



11. The project manager is normally directly accountable for the project results, schedule and budget.


ANS: T DIF: Easy REF: 1.5 OBJ: Identify key roles



12. The project manager is typically the keeper, facilitator and improver of the project management
system.


ANS: F DIF: Average REF: 1.5 OBJ: Identify key roles

,13. All projects go through a common project life cycle that includes four stages: concept,
development, production and close-out.


ANS: F DIF: Easy REF: 1.3 OBJ: Life cycle stages



14. The name and number of phases in a project life cycle are determined by the organization(s)
involved in the project.


ANS: T DIF: Average REF: 1.3 OBJ: Life cycle stages



15. An important factor used to determine the phases in a project life cycle are the control needs of
the organization(s) involved in the project.


ANS: T DIF: Average REF: 1.3 OBJ: Life cycle stages



16. Project customers can be either internal or external to the organization.


ANS: T DIF: Easy REF: 1.3 OBJ: Life cycle stages



17. Different project life cycle models are used for different types of projects.


ANS: T DIF: Easy REF: 1.3 OBJ: Life cycle stages



18. Generally, project life cycle stages are designed so that the amount of money spent in each of the
stages is nearly equivalent.


ANS: F DIF: Average REF: 1.3 OBJ: Life cycle stages



19. Scope management generally entails defining, sequencing and estimating the duration of project
activities.

, ANS: F DIF: Average REF: 1.4 OBJ: Issues for knowledge
areas



20. Quality management generally entails risk identification, analysis and response planning.


ANS: F DIF: Average REF: 1.4 OBJ: issues for knowledge
areas



21. Human Resource management generally entails acquiring, developing and managing the project
team.


ANS: T DIF: Easy REF: 1.4 OBJ: Issues for knowledge
areas



22. Cost management generally includes planning, estimating and controlling costs.


ANS: T DIF: Easy REF: 1.4 OBJ: Issues for knowledge
areas




MULTIPLE CHOICE



1. Which of the following examples is NOT a typical or appropriate situation to employ project
management?



a. improving an existing work process

b. installing a new computer system

c. conducting a routine, standard customer service operation

d. developing a new product

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
tb4u City University New York
Follow You need to be logged in order to follow users or courses
Sold
971
Member since
3 year
Number of followers
776
Documents
2374
Last sold
1 day ago

4,0

158 reviews

5
87
4
27
3
19
2
6
1
19

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can immediately select a different document that better matches what you need.

Pay how you prefer, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card or EFT and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions