For positive pressure supply systems, control mechanisms peak calculated demand
A) 50%
B) 100%
C) 150%
D) 250%C) 150%
D) 250% - ANSWERB) 100% 5.1.3.5.5.1(2)
ASSE CERTIFICATION FOR INSTALLERS
A) 6030
B) 6020
C) 6010
D) 6040 - ANSWERC) 6010 2.3.4
PIPING SHALL BE LABELED BY STENCILING OR ADHESIVE MARKERS AND
SHALL
A) EVERY 20 FEET
B) AT LEAST 1 TIME IN EVERY ROOM
C) AT LEAST 1 TIME EVERY STORY
D) ALL THE ABOVE - ANSWERD) ALL THE ABOVE 5.1.11.1
The minimum number of exits for outdoor enclosures on bulk cryogenic liquid
systems
A) 1
B) 2
C) 3
D) 4 - ANSWERB) 2 5.1.3.3.2(5)
When system gas is used for testing, it shall be tested at ?
A) Most remote outlet
B) Closest Outlet
C) Equipment
D) Before Tie in - ANSWERC) Equipment 5.1.12.4.8.3
When is the initial pressure test conducted
A) After blowdown of distribution piping
B) After installation of outlet/inlet rough-in assemblies
C) Prior to installation of components that would be damaged by test pressure
D) All of the above - ANSWERD) All of the above 5.1.12.2.3.2
Inlets/Outlets shall be identified with name of gas or vacuum
A) TRUE
B) FALSE - ANSWERA) TRUE 5.1.5.5 5.1.11.3