The purpose of the Deploy All Resources Action is to instruct all generating
resources to be on line and at full output _________ - 🧠 ANSWER
✔✔immediately upon receipt of dispatch instruction
A Heavy Load Voltage Schedule Warning has been issued for the PJM
RTO. Generation Operators should: - 🧠 ANSWER ✔✔Ensure all unit
voltage regulators are in service
PJM can issue the Deploy All Resources Action for________ - 🧠 ANSWER
✔✔the entire RTO, specific Control Zones or a subset of a Control Zone if
transmission limitations exist
, Under the National Terrorism Advisory System (NTAS) there are 2 types of
alerts: Elevated Threat Alert and __________. - 🧠 ANSWER ✔✔Imminent
Threat Alert
A Geomagnetic Disturbance Warning is issued by PJM when the NOAA
has issued a warning or an alert for a potential geo-magnetic storm of
severity _______ or greater. - 🧠 ANSWER ✔✔K7
The Generating Capacity reported on a Supplementary Status Report
(SSR) includes which of the following? (Select 2) - 🧠 ANSWER ✔✔Capacity
from offline Hydro and CT units that can be synchronized within 10
minutes.
Total Capacity from online Generation.
What is the requested response time for members to reply to a request for
SSR data? - 🧠 ANSWER ✔✔10 Minutes
If a PJM Member has received reports of a terrorism or sabotage threat to
their facilities, they would notify whom at PJM (in addition to NERC and the
DOE) to share this information? - 🧠 ANSWER ✔✔The PJM Shift Supervisor
What is the purpose of a capacity emergency warning? (Select 2) - 🧠
ANSWER ✔✔To keep Members informed of actual capacity shortages or