QUESTIONS WITH ACCURATE
ANSWERS | MULTIPLE CHOICES |!!
Question 1:
How must a client submit a claim for service or repair of a defect on fit and
finish items after a remodel?
A.) by certified mail
B.) by overnight mail
C.) by personal delivery
,D.) any of the above - 🧠 ANSWER ✔✔D. A client may use the normal
customer-service procedures agreed to between the client and the
contractor, but the client must notify the contractor of the defect in writing
by certified mail, overnight mail, or personal delivery before the client may
file an action in court.
Question 2:
What is the maximum allowed travel distance from any point of a work area
to a fire extinguisher?
a.)25 feet
b.)50 feet
c.)75 feet
d.)150 feet - 🧠 ANSWER ✔✔75 feet
,When should you renew contractors bond? - 🧠 ANSWER ✔✔30 days
before bond expires
Question 4:
If, during excavation, you unearth human remains or burial artifacts at a
construction site, what should you do?
Click here to select answer B.
Notify the owner of the property.
Click here to select answer B.
Stop work and place a warning ribbon three feet from the remains around
the perimeter of the site.
Click here to select answer C.
Stop work immediately at that site.
Click here to select answer D.
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED
, Stop work immediately at that site and any other nearby area that may
have remains. - 🧠 ANSWER ✔✔Stop work immediately at that site and any
other nearby area that may have remains.
Question 5:
Direct costs are $37,000, overhead is 12%, and profit is 5%. What is the
selling price?
Click here to select answer A.
$39,272.47
Click here to select answer B.
$41,373.45
Click here to select answer C.
$43,383.37
Click here to select answer D.