BANK ACCURATE REAL EXAM
WITH COMPLETE QUESTIONS AND
VERIFIED ANSWERS | EXPERTLY
VERIFIED FOR GUARANTEED PASS
What is the required Cranes and Derricks approved form
for the designated A/D Director onsite: -
....ANSWER...CD-8 A/D
Chapter 33, Section 3305.3.2.6.3- Where shore height
exceeds feet, or when necessary to provide structural
stability, diagonal bracing shall be provided. -
....ANSWER...10 ft
. Who is exempt from the requirements of Local Law 52 of
2005 (Supported Scaffold Training)? -
....ANSWER...Properly trained public utility
employee
According to Table 3314.5.2, full thickness lumber (2
inches) spanning 8 feet will result in a working load of
1
, ? Please refer to your chapter 33 book for the
table. - ....ANSWER...50 psf (medium duty
scaffold)
When chutes are more than 75 feet in height they shall be
constructed using: - ....ANSWER...24-gauge steel
sheeting
What is the minimum bumper or curb for a floor level
chute opening? - ....ANSWER...4" x 4"
Sidewalk sheds. A vertical parapet at least 3 feet 6 inches
(1067 mm) high, as measured from the deck of the
sidewalk shed, shall be constructed along all edges of the
sidewalk shed. Such parapet shall consist of solid plywood,
corrugated metal, a galvanized wire screen consisting of
not less than . - ....ANSWER...No. 16 steel
wire gage with a 1⁄2-inch (13 mm) debris mesh
The top rail of a standard guardrail must be capable of
withstanding without failure . - ....ANSWER...A
force of 200 lbs.
2
, What is the maximum allowable loading for an outrigger
scaffold? - ....ANSWER...50 PSF
All (non-scaffold) platforms require a standard guardrail
at a height of above the adjoining ground? -
....ANSWER...5 feet
Before leaving a crane or derrick unattended, the operator
shall: - ....ANSWER...Put controls in the "off" position