100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Project Management Fbla Exam Questions With 100- Verified Answers.docx

Rating
-
Sold
-
Pages
5
Grade
A+
Uploaded on
03-12-2025
Written in
2025/2026

Project Management Fbla Exam Questions With 100- Verified A

Institution
FBLA
Course
FBLA









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
FBLA
Course
FBLA

Document information

Uploaded on
December 3, 2025
Number of pages
5
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Project Management Fbla Exam
Questions With 100% Verified Answers
What is a stakeholder -
correct answer ✅A stakeholder is an individual, group, or
organization who may affect, be affected by, or perceive itself to be
affected by a decision, activity, or outcome of a project.


Interactive communication -
correct answer ✅Between two or more parties performing a
multidirectional exchange
of information. It is the most efficient way to ensure a common
understanding by all participants on
specified topics, and includes meetings, phone calls, instant
messaging, video conferencing, etc.


Push communication. -
correct answer ✅Sent to specific recipients who need to receive
the information. This ensures
that the information is distributed but does not ensure that it
actually reached or was understood by the
intended audience. Push communications include letters, memos,
reports, emails, faxes, voice mails,
blogs, press releases, etc.

, Project Management Fbla Exam
Questions With 100% Verified Answers
Pull communication -
correct answer ✅Used for very large volumes of information, or
for very large audiences, and
requires the recipients to access the communication content at
their own discretion. These methods
include intranet sites, e-learning, lessons learned databases,
knowledge repositories, etc.


Schedule variance. -
correct answer ✅Schedule variance (SV) is a measure of schedule
performance expressed as the
difference between the earned value and the planned value. It is
the amount by which the project is ahead
or behind the planned delivery date, at a given point in time. It is a
measure of schedule performance on
a project. It is equal to the earned value (EV) minus the planned
value (PV). The EVM schedule variance is
a useful metric in that it can indicate when a project is falling
behind or is ahead of its baseline schedule.
The EVM schedule variance will ultimately equal zero when the
project is completed because all of the

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Cindellera stuvia
View profile
Follow You need to be logged in order to follow users or courses
Sold
99
Member since
1 year
Number of followers
2
Documents
10094
Last sold
12 hours ago

4.0

23 reviews

5
10
4
6
3
5
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions