where should the machine room light switch be located
on the lock jamb side of the door
you arrive at a job and notice the counterweight has a governor. what does this mean
there's an occupied space below
you are performing a final acceptance test on a 700fpm elevator. at what percent of the
mechanical trip speed should the electrical overspeed switch trip
not more than 95%
why is it necessary that a governor be mounted a a steel channel section (high rise)
to support the extra weight of the governor rope
you are performing routine maintenance on a governor, just have to paint it. what test should
you do to make sure all parts move freely
hand test
you have installed hoistway slowdown switches on brackets attached to the main guide rails.
what other component actuates these
cam on the car
for a 5 year safeties test on a car rated 4000lb, how much weight is needed
4000lbs
you just installed the controller. its out of plumb, what do you do
1|Page
,shim it
you need to ensure electrical continuity. what is this process called
bonding
you are installing a class B freight. according to asme what is the max acceptable load for the
elevator
automobiles up to rated loaded capacity
you are installing a passenger elevator. how many pieces is the platform
one
you are preparing the assemble the car sling on a hydro. what are the components
crosshead, stiles, bolster channel
for a broken rope type safety- after slackening the hoist ropes, when do the safeties engage the
rail
immediately
you are performing an acceptance test with type B flexible guide safeties. after initial
application, what provides the final force in the safety jaw assembly
spring
after installing the compensating sheave, you prepare to attach the comp ropes. where will the
ropes attach
under the car
you have installed a high rise traction and notice it slips traction at the top and bottom floors.
what must be installed to counteract this
comp ropes/chains
you need to determine runby clearance. between which points do you measure
counterweight and strike plate
the elevator you are working on is counterbalanced at 40% and the total car weight is 3000lb.
the capacity load is 2500lb. you must load the counterweight frame. what should the total
weight of the frame be
4000lbs
2|Page
, while performing maintenance on an elevator, you notice a lack of lubrication on the suspension
means, what could be a consequence if this is not addressed
loss of cable diameter
when inspecting preformed/non preformed ropes for wear, what is an important consideration
it is more difficult to detect broken wires on preformed
you should compare the governor rope tag to what
governor data plate
you have set up the car and counteweight for rope replacement and have landed the
counterweight on two metal stanchions. at what capacity must these stanchions be rated
each stanchion must be capable of supporting the entire load
you are reroping and elevator and have selected two chainfalls to hang the car. the total weight
of the car is 4000. what should be the minimum capacity of each chain fall
4000 lbs
you will be replacing hoist ropes and must make preparations with the customer. what
important scope of work must be discussed
space required to perform work
you are performing a 1:1 rope replacement. where in the hoistway should you rig the car
middle
you are ready to cut the dead end excess after reshackling. how far past the socket should you
cut it
6-9"
new shackles are installed. how should the dead end be secured?
retainer clips
you are tensioning the ropes on an elevator that has two different length of shackles. how must
you tension the ropes
shackles must be equally tensioned
what type of stretch is reduced using pre stretched rope
constitutional stretch