◉ according to the Texas mold assessment and remediation rules, a
mold assessment consultant may perform an assessment to.
Answer: collect data for writing a mold assessment report
◉ health effects from inhalation of mold spores could be. Answer:
Hypersensitivity pneumonitis
◉ according to the Texas mold assessment and remediation rules,
mold is defines as. Answer: spores, hyphae, mycotoxins, and living or
dead fungi
◉ according to the Texas mold assessment and remediation rules,
the purpose of a mold assessment is to. Answer: determine the
sources, locations and extent of mold growth in a building /
determine the condition(s) that caused the mold growth / and
enable the assessment consultant to prepare a mold remediation
protocol
◉ according to the Texas mold assessment and remediation rules, a
licensed mold assessment company or consultant shall maintain
,records until. Answer: the company or consultant issues a mold
assessment report, management plan, or remediation protocol to a
client, if the company or consultant performs. only the initial
assessment for the project / the company or consultant issues the
final. status report to the client, if a. final status report is issued /
and the company or consultant provides the. signed. certificate of
mold remediation to a mold remediation contractor or company, if a
certificate of mold remediation is provided
◉ according to the Texas mold assessment and remediation rules, a
post remediation assessment shall determine if. Answer: the work
area is free of all visible mold and wood rot / all work has been
completed in compliance with the remediation protocol and work
plan and meets clearance criteria specified in the protocol
◉ according to the Texas mold assessment and remediation rules,
notice signs for mold remediation projects must say. Answer:
NOTICE: mold remediation project in progress
◉ according to the Texas mold assessment and remediation rules,
containment is not required for a contaminated area of less than.
Answer: 25 continguous square feet
◉ according to the Texas mold assessment and remediation rules,
the stop date is defined as. Answer: the date after the date on which
final clearance is achieved
, ◉ according to the Texas mold assessment and remediation rules,
the start date is defined as. Answer: the date on which the actual
remediation begins
◉ according to table. 2 of the EPA's "Mold remediation in schools
and commercial buildings", it is recommended that a carpeted area
of 50 square feet that has mold contamination from clean water
should be. Answer: wet vacuumed, HEPA vacuumed or discarded
well-sealed plastic bags
◉ according to table. 2 of the EPA's "Mold remediation in schools
and commercial buildings, the containment recommended for a
contaminated area of less than 10 ft.² is. Answer: none
◉ according to the Texas mold assessment and remediation rules,
notice signs for mold remediation projects must be. Answer: 8
inches by 10 inches in size
◉ according to table one of the EPA's mold remediation in schools of
commercial buildings, if clean water damage has occurred within 24
hours to 48 hours, it is recommended that cellulose insulation be.
Answer: discarded and replaced