VA DEQ
"Conserved" open areas should be ______________ in to be considered as open space in the
VRRM. - ANS-Undisturbed
A permeable pavement gadget with out an undrain have to have an infiltration fee of: -
ANS-zero.Five" in step with hour or extra
A sediment trap collects from regions that are_____. - ANS-< three acres
A stormwater management facility will be inspected by way of the accountable kingdom
business enterprise on a ____ basis and after any typhoon that causes the capacity of the
facility's precept spillway to be handed. - ANS-Annually
A VSMP authority can trouble _____ as enforcement. - ANS-Verbal warnings, Notice of
Correction, Consent Orders, Notice to Comply
All ESC plans encompass a _______ for the ESC measures used. - ANS-a announcement
describing the protection responsibilities required
Application Packages require: - ANS--SWPPP
-Long time period Maintenance Agreement
-Bond
-Fees
-Registration Statement
Are wetlands required to have sediment forebays? - ANS-Yes, sediment forebays are required
to be at each inlet to a constructed wetland.
As a Stormwater Inspector, are you accountable for inspecting any assist sports worried with a
assignment? - ANS-Yes, under the CGP you must look into the web sites in which assisting
activities are taking place.
Can grass channels be used in karst regions? - ANS-Yes, so long as they don't deal with
hotspot runoff.
Can soil amendments be incorporated into karst regions? - ANS-Yes so long as they do not deal
with hotspot runoff.
, Certificates of competency are legitimate for ____. - ANS-3 years
Construction report drawings ought to be stored for the way lengthy? - ANS-Until the stormwater
facility is removed
Define the Virginia Runoff Reduction Method. - ANS-A compliance approach used in VA to cope
with pollutant loads through incorporating ESD, runoff treatment, and extent manipulate
alternatives.
End date for 2C standards - ANS-June 30, 2019 (Grandfathered projects), June 30, 2024 (Time
Limits on Applicability)
Exceptions to the technical requirements of element 2B or component 2C may not be granted
for: - ANS--Economic hardship alone
-Obtaining required nation lets in
-Use of a BMP not in the Stormwater BMP Clearinghouse
Exemptions to the SWM software: - ANS-Mining operations, land clearing for Agricultural
functions, unmarried-own family houses annoying < 1 acre, discharges to a sanitary or
combination sewer, activities executed underneath a reclamation venture, routine protection to
preserve unique situations, LDAs in reaction to a public emergency
Final Stabilization - ANS-When a uniform, evenly dispensed perennial vegetative cover with a
density of 70% of the local history cowl has been hooked up on all unpaved areas and areas
now not blanketed by means of everlasting systems.
For a level 1 moist swale, what is the whole phosphorus removal percent? - ANS-20%
For drainage regions <= 200 acres, the VSMP may allow for the use of: - ANS-The Rational
Method
Grass channels should be seeded at a density such that __________% of grass survives after
the 2nd growing season. - ANS-90%
How can oil / fuel spills be prevented from discharging off of a site? - ANS-1. Use a secondary
containment method (spill berms, decks, etc.)
2. Cover the area with an impermeable sheet.
3. Have spill kits near by.
How far does water travel as sheet flow before it starts to become concentrated flow? -
ANS-100 feet
How much total volume (Tv) should a level 1 extended detention pond have? - ANS-A minimum
of 15% of the total volume in the permanent pool.