This document contains the complete and verified solutions for the California UST (Underground Storage Tank) Service Technician Part 1 Exam for the 2025/2026 licensing cycle. It covers all required topics under the California State Water Resources Control Board (SWRCB) certification standards, including UST system components, leak detection, secondary containment testing, maintenance and repair procedures, and environmental compliance. Designed for technicians preparing for state certification, this guide ensures full understanding of California UST laws, operational protocols, and safety regulations.

Show more Read less
Institution
California UST
Course
California UST











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
California UST
Course
California UST

Document information

Uploaded on
November 11, 2025
Number of pages
31
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • complete exam

Content preview

CALIFORNIA UST SERVICE TECHNICIAN PART 1 — COMPLETE
SOLUTIONS (2025/2026)

Introduction

The California Underground Storage Tank (UST) Service Technician Part 1 certification
ensures technicians are equipped to maintain, test, and monitor UST systems in
compliance with state regulations, protecting public health and the environment. This
exam covers critical areas including UST system components, leak detection, California
Code of Regulations Title 23 requirements, testing procedures (sensors, spill buckets,
sumps, ATG systems, secondary containment), permit-to-operate rules, monitoring
plans, maintenance, recordkeeping, environmental protection, and site assessments.
Designed for the 2025/2026 regulatory cycle, this content provides original,
scenario-based questions with detailed explanations for technical mastery, formatted in
Markdown for clarity and professionalism.


Question 1
During an annual inspection, a technician finds a spill bucket with 2 inches of standing
liquid. What is the first action required under California Title 23?
A. Ignore if the liquid is clean water
B. Drain and clean the spill bucket
C. Report to the local agency immediately

D. Replace the spill bucket

Correct Answer: B — Drain and clean the spill bucket

Explanation: California Title 23, Chapter 16 requires spill buckets to be free of liquid and
debris to ensure proper function (Section 2635). The first action is to drain and clean the
bucket, then inspect for damage. Ignoring (A) risks contamination, reporting (C) is
premature, and replacement (D) is unnecessary without further assessment.

Question 2
Which component of a UST system prevents fuel from entering the environment during
overfill?
A. Interstitial sensor
B. Flapper valve
C. Sump pump

D. ATG probe

Correct Answer: B — Flapper valve

,Explanation: Flapper valves are overfill prevention devices that restrict fuel flow during
delivery when the tank reaches capacity, preventing spills (Title 23, Section 2636).
Interstitial sensors (A) detect leaks, sump pumps (C) remove liquid, and ATG probes (D)
monitor levels.

Question 3
A technician calibrates an ATG system. How often must calibration be performed per
California regulations?
A. Monthly
B. Annually
C. Every three years

D. Only after repairs

Correct Answer: B — Annually

Explanation: Title 23, Section 2638 requires annual calibration of automatic tank gauge
(ATG) systems to ensure accurate monitoring. Monthly (A) is incorrect, triennial (C)
applies to other tests, and calibration after repairs (D) is additional, not exclusive.

Question 4
What is the minimum detection capability for a continuous interstitial monitoring
system?
A. 0.1 gallons per hour
B. 0.2 gallons per hour
C. 1 gallon per day

D. 3 gallons per month

Correct Answer: A — 0.1 gallons per hour

Explanation: California Title 23, Section 2643 mandates that continuous interstitial
monitoring systems detect leaks at a minimum of 0.1 gallons per hour to ensure early
identification of releases. Other options (B, C, D) do not meet this standard.

Question 5
A UST site lacks a current permit-to-operate. What must the technician do?
A. Continue operations until renewal
B. Notify the local agency within 24 hours
C. Cease fuel dispensing immediately

D. Submit a new monitoring plan

Correct Answer: C — Cease fuel dispensing immediately

,Explanation: Title 23, Section 2712 prohibits UST operations without a valid
permit-to-operate. Dispensing must stop until compliance is restored. Continuing (A),
notifying (B), or submitting a plan (D) does not address the immediate violation.

Question 6
Which test is required triennially for secondary containment systems?
A. Hydrostatic testing
B. Vacuum testing
C. Statistical inventory reconciliation

D. Sensor functionality test

Correct Answer: A — Hydrostatic testing

Explanation: Title 23, Section 2637 requires hydrostatic testing of secondary containment
systems every three years to verify integrity. Vacuum testing (B) is less common, SIR (C)
is for leak detection, and sensor tests (D) are annual.

Question 7
A sump sensor triggers an alarm. What is the technician’s first step?
A. Replace the sensor
B. Inspect the sump for liquid
C. Disable the alarm

D. Report to the state water board

Correct Answer: B — Inspect the sump for liquid

Explanation: Title 23, Section 2632 requires immediate investigation of sensor alarms,
starting with inspecting the sump for liquid to identify leaks. Replacing (A), disabling (C),
or reporting (D) without inspection is premature.

Question 8
What is the purpose of a monitoring plan for a UST facility?
A. To schedule fuel deliveries
B. To outline leak detection and response procedures
C. To document tank installation

D. To track employee certifications

Correct Answer: B — To outline leak detection and response procedures

Explanation: Title 23, Section 2711 mandates that monitoring plans detail leak detection
methods, equipment, and emergency response protocols to ensure compliance. Other
options (A, C, D) are unrelated to the plan’s purpose.

, Question 9
A technician observes corrosion on a riser pipe. What is the required action?
A. Ignore if minor
B. Clean and coat the pipe
C. Replace the pipe immediately

D. Report to the local agency within 48 hours

Correct Answer: C — Replace the pipe immediately

Explanation: Title 23, Section 2660 requires immediate replacement of corroded
components like riser pipes to prevent leaks. Ignoring (A), cleaning (B), or reporting (D)
does not address the structural risk.

Question 10
Which leak detection method analyzes daily inventory records for discrepancies?
A. Interstitial monitoring
B. Statistical inventory reconciliation (SIR)
C. Soil vapor monitoring

D. Automatic tank gauging

Correct Answer: B — Statistical inventory reconciliation (SIR)

Explanation: SIR analyzes daily inventory data to detect leaks statistically, as per Title 23,
Section 2643. Interstitial monitoring (A) uses sensors, soil vapor (C) tests ground, and
ATG (D) monitors tank levels directly.

Question 11
What is the maximum allowable liquid in a spill bucket during delivery?
A. None
B. 1 inch
C. 2 inches

D. 3 inches

Correct Answer: A — None

Explanation: Title 23, Section 2635 requires spill buckets to be free of liquid during
delivery to ensure capacity for potential spills. Any liquid (B, C, D) indicates
non-compliance.

Question 12
A technician must maintain records of sensor tests for how long?
A. 1 year
B. 3 years
$10.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
TutorAgness
5.0
(1)

Get to know the seller

Seller avatar
TutorAgness Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
8
Member since
1 year
Number of followers
5
Documents
298
Last sold
3 weeks ago

5.0

1 reviews

5
1
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions