A feature should be sized to fit into what duration?
A. One month
B. One year
C. One PI
D. One Iteration - ANSC. One PI
A SAFe Portfolio is a collection of what?
A. Development Value Streams
B. Functional teams
C. Solutions
D. Business units - ANSA. Development Value Streams
According to SAFe Lean-Agile Principle #10, what should the Enterprise do
when markets and customers demand change?
A. Apply development cadence & synchronization to operate effectively &
manage uncertainty
B. Create a new Portfolio to manage the change
C. Create a reliable decision-making framework to empower employees
D. Reorganize the network to address emerging opportunities - ANSD.
Reorganize the network to address emerging opportunities
1
, 2
Deploy, verify, monitor, & respond are all activities of what?
A. Continuous Integration
B. Continuous Exploration
C. Continuous Deployment
D. Release on Demand - ANSC. Continuous Deployment
During System Demo, Team B states that the most recent release failed
because of poor version control. They share their plan for preventing
similar mistakes from happening in the future. Which of the following SAFe
Core Values is Team B demonstrating?
A. Organize around value
B. Siloed Thinking
C. Transparency
D. Visualizing work - ANSC. Transparency
During the final plan review, ART PI risks are ROAM'ed. What do the letters
in ROAM represent?
A. Resolved, Owned, Approved, Mitigated
B. Resolved, Owned, Accepted, Mitigated
C. Resolved, Owned, Assigned, Mitigated
D. Resolved, Owned, Active, Mitigated - ANSB. Resolved, Owned,
Accepted, Mitigated
2
, 3
During the Innovation and Planning Iteration, an organization invites every
team member to work on any project they chose. Which of the following
SAFe Core Values is the organization demonstrating?
A. Siloed thinking
B. Relentless improvement
C. Make value flow without interruptions
D. Visualizing work - ANSB. Relentless improvement
During the PI Planning event, when are planning adjustments agreed
upon?
A. During breakout sessions
B. During the draft plan review
C. During the Coach sync
D. During the management review and problem-solving meeting - ANSD.
During the management review and problem-solving meeting
During which of the following PI Planning activities are Business Owners
asked to accept the plans?
A. The second team breakout session
B. The draft plan review
C. The Management Review and Problem-Solving workshop
D. The final plan review - ANSD. The final plan review
3
, 4
During which of the following PI Planning activities does Product
Management introduce the prioritized Features to the teams for planning?
A. The Product/Solution Vision presentation
B. The draft plan review
C. The business context presentation
D. The Management Review and Problem-Solving workshop - ANSA. The
Product/Solution Vision presentation
During which PI planning activity are Stories written and sequenced?
A. The team breakout session
B. The draft plan review
C. The management Review and Problem-Solving workshop
D. The business context presentation - ANSA. The team breakout session
During which PI Planning activity do Business Owners assign business
value to PI Objectives?
A. The final plan review
B. The team breakout session
C. The Management Review and Problem-Solving workshop
D. The draft plan review - ANSB. The team breakout session
During which PI planning activity do team members commit to do
everything they can to meet the agreed-to-objectives?