In the UCF, Contract administration data is found in which section? -
ANSWERS-Section G
FAR 15.204-2(g)
In the UCF, Deliveries or performance is found in which section? -
ANSWERS-Section F
FAR 15.204-2(f)
In the UCF, description/specifications/statement of work is found in which
section? - ANSWERS-Section C
See FAR 15.204-2(f).
Where in the FAR and DFARS are the text of provisions and clauses
found? - ANSWERS-The text of provisions and clauses are found in FAR
subpart 52.2 and DFARS subpart 252.2.
If the clause at FAR 52.242-15, Stop Work-Order, is required to be in your
solicitation, it would be in which section? - ANSWERS-section F
,See the FAR Matrix at https://www.acquisition.gov/far-smart-matrix ; click
the UCF block Step 1 and look up FAR 52.242-15; look at the UCF column
to see that the clause would be included in section F.
True or False:
Because this is a competitive negotiation you are not required to address
the relative order of importance of the evaluation factors. - ANSWERS-This
statement is false. See FAR 15.101-1(b)(2), when using the tradeoff
process you would be required to address the order of importance of the
evaluation factors.
Where in the FAR do you look to find information on Publicizing Contract
Actions? - ANSWERS-FAR part 5
What is the purpose of and policy for publicizing information? - ANSWERS-
Increase competition
Broaden industry participation in meeting Government requirements
Assist small business concerns
See FAR 5.002.
What type of notice would you use to post your draft RFP? - ANSWERS-
Special and Presolicitation
,Although FAR 5.205(c) states a Special notice may be used when
publicizing draft solicitations and draft specifications. It is also common
practice for some organizations to use a presolicitation notice to publicize a
draft RFP.
How many days must you provide for industry to respond to the draft RFP?
- ANSWERS-A reasonable opportunity to respond
There is no specified limit
The FAR does not provide any guidance or limitations on how long you
must allow for industry to respond to a draft RFP. In your training you have
learned that a reasonable opportunity to respond should be considered in
order to increase competition, improve potential responses, and decrease
risk.
What is the purpose of exchanging information with industry (potential
offerors)? - ANSWERS-Allows potential offerors to judge if they can satisfy
the Government's requirements
Enhances the Government's ability to obtain quality at reasonable prices
Increases efficiency in proposal preparation, proposal evaluation,
negotiation, and contract award
See FAR 15.201(b), Exchanges with Industry Before Receipt of Proposals.
, Fill in the blank. When it comes to inquiries about a specific acquisition, the
general rule is that only ___________ may answer a prospective offeror's
inquiry about the acquisition. - ANSWERS-the contracting officer with
contractual authority
See FAR 15.201(f), which provides that the contracting officer must be the
focal point of any exchange with potential offerors.
Where in the FAR are exchanges with industry before receipt of proposals
covered? - ANSWERS-FAR 15.201
Where in the FAR directs us to act fairly and without preferential treatment.
- ANSWERS-FAR part 3
To whom must you provide a copy of all questions and answers generated
by the draft RFP? - ANSWERS-All prospective offerors
See FAR 15.201(f), which states that when specific information about a
proposed acquisition that would be necessary for the preparation of
proposals is disclosed to one or more potential offerors, that information
must be made available to the public as soon as practicable, but no later
than the next general release of information, in order to avoid creating an
unfair competitive advantage.