Con 367 Exam 1 Questions With Correct
Answers
Professional |CM |(Agency |CM) |- |CORRECT |ANSWER✔✔-Which |one |of |the |following |is |not |a |
Project |Delivery |System?
In |lump-sum |contracts, |the |Owner |assumes |the |risk |of |cost. |- |CORRECT |ANSWER✔✔-False
Typically, |the |Design |Reviewer |has |the |ultimate |responsibility |and |authority |to |make |executive |
decisions |related |to |matters |affecting |time |and |money |in |a |construction |project. |- |CORRECT |
ANSWER✔✔-False
In |the |Design-Build |project |delivery |system, |the |Owner |has |separate |contracts |with |the |
Designer |and |the |Contractor. |- |CORRECT |ANSWER✔✔-False
The |Resident |Project |Representative |should |stop |the |work |of |the |Contractor |when |the |work |is |
not |performed |according |to |the |drawings |and |specifications. |- |CORRECT |ANSWER✔✔-False
Which |of |the |following |should |not |be |performed |by |the |Resident |Project |Representative |for |
inspections? |- |CORRECT |ANSWER✔✔-Providing |instructions |directly |to |subcontractors
Which |of |the |following |is |not |true |for |the |construction |diary? |- |CORRECT |ANSWER✔✔-Entries |
should |be |made |on |a |weekly |basis |(i.e., |at |the |end |of |each |week)
Ambiguous |language |in |a |contract |is |interpreted |against |the |party |who |selected |the |language |
or |supplied |the |contract. |- |CORRECT |ANSWER✔✔-True
, According |to |Spearin |Doctrine, |when |the |contractor |exactly |follows |the |detail |specifications |
and |drawings, |she/he |will |not |be |responsible |for |unsatisfactory |results |in |the |end |product. |- |
CORRECT |ANSWER✔✔-True
Shop |drawings |can |be |used |as |change |orders. |- |CORRECT |ANSWER✔✔-False
Which |one |of |the |following |is |not |an |element |of |the |Contract |as |we |discussed |in |class? |- |
CORRECT |ANSWER✔✔-(Promise)
| Offer |
| Acceptance |
| Consideration
Which |of |the |following |is |not |a |condition |where |a |contract |will |not |be |enforced |by |courts? |- |
CORRECT |ANSWER✔✔-Seniority
Fill |in |the |blank |in |the |following |statement: |Some |contracts |must |be |in |writing |under |the |
____________ |as |adopted |by |each |state. |- |CORRECT |ANSWER✔✔-Statute |of |Frauds
RFI |(Request |for |Information) |is |the |document |that |is |transmitted |to |the |General |Contractor |
from |the |Designer |to |get |clarifications |with |respect |to |design |drawings |and |specifications. |- |
CORRECT |ANSWER✔✔-False
The |resident |project |representative |should |not |supervise, |direct, |or |control |the |contractor's |
means |and |methods |of |performing |work. |- |CORRECT |ANSWER✔✔-True
In |fast-track |projects |with |multiple |contractors, |the |services |of |a |professional |construction |
management |firm |(Agency |CM) |are |essential. |- |CORRECT |ANSWER✔✔-True
Answers
Professional |CM |(Agency |CM) |- |CORRECT |ANSWER✔✔-Which |one |of |the |following |is |not |a |
Project |Delivery |System?
In |lump-sum |contracts, |the |Owner |assumes |the |risk |of |cost. |- |CORRECT |ANSWER✔✔-False
Typically, |the |Design |Reviewer |has |the |ultimate |responsibility |and |authority |to |make |executive |
decisions |related |to |matters |affecting |time |and |money |in |a |construction |project. |- |CORRECT |
ANSWER✔✔-False
In |the |Design-Build |project |delivery |system, |the |Owner |has |separate |contracts |with |the |
Designer |and |the |Contractor. |- |CORRECT |ANSWER✔✔-False
The |Resident |Project |Representative |should |stop |the |work |of |the |Contractor |when |the |work |is |
not |performed |according |to |the |drawings |and |specifications. |- |CORRECT |ANSWER✔✔-False
Which |of |the |following |should |not |be |performed |by |the |Resident |Project |Representative |for |
inspections? |- |CORRECT |ANSWER✔✔-Providing |instructions |directly |to |subcontractors
Which |of |the |following |is |not |true |for |the |construction |diary? |- |CORRECT |ANSWER✔✔-Entries |
should |be |made |on |a |weekly |basis |(i.e., |at |the |end |of |each |week)
Ambiguous |language |in |a |contract |is |interpreted |against |the |party |who |selected |the |language |
or |supplied |the |contract. |- |CORRECT |ANSWER✔✔-True
, According |to |Spearin |Doctrine, |when |the |contractor |exactly |follows |the |detail |specifications |
and |drawings, |she/he |will |not |be |responsible |for |unsatisfactory |results |in |the |end |product. |- |
CORRECT |ANSWER✔✔-True
Shop |drawings |can |be |used |as |change |orders. |- |CORRECT |ANSWER✔✔-False
Which |one |of |the |following |is |not |an |element |of |the |Contract |as |we |discussed |in |class? |- |
CORRECT |ANSWER✔✔-(Promise)
| Offer |
| Acceptance |
| Consideration
Which |of |the |following |is |not |a |condition |where |a |contract |will |not |be |enforced |by |courts? |- |
CORRECT |ANSWER✔✔-Seniority
Fill |in |the |blank |in |the |following |statement: |Some |contracts |must |be |in |writing |under |the |
____________ |as |adopted |by |each |state. |- |CORRECT |ANSWER✔✔-Statute |of |Frauds
RFI |(Request |for |Information) |is |the |document |that |is |transmitted |to |the |General |Contractor |
from |the |Designer |to |get |clarifications |with |respect |to |design |drawings |and |specifications. |- |
CORRECT |ANSWER✔✔-False
The |resident |project |representative |should |not |supervise, |direct, |or |control |the |contractor's |
means |and |methods |of |performing |work. |- |CORRECT |ANSWER✔✔-True
In |fast-track |projects |with |multiple |contractors, |the |services |of |a |professional |construction |
management |firm |(Agency |CM) |are |essential. |- |CORRECT |ANSWER✔✔-True