brick on a job site should be covered - 🧠ANSWER ✔✔when you leave at
the end of the day
how long should tile set on a organic adhesive bed in order to cure -
🧠ANSWER ✔✔24 hours
what is the correct space (gap) between a finished floor and bottom of an
interior door with no threshold - 🧠ANSWER ✔✔1/2"
what are as built plans - 🧠ANSWER ✔✔plans showing all changes and
repair
can you directly nail hardwood flooring to a concrete slab - 🧠ANSWER
✔✔no you should never nail it directly
, interior carpet should be installed with - 🧠ANSWER ✔✔tackless strips
before applying latex paint to the surface of an oil paint on wood trim which
procedure is appropriate - 🧠ANSWER ✔✔wash with tsp
handicap sinks should have what kind of drains - 🧠ANSWER ✔✔wrapped
handicap restrooms should have - 🧠ANSWER ✔✔a min of 48"
maneuverable space in front of toilet
lever handles on faucet
wrapped drain lines
an MSDS should be kept at - 🧠ANSWER ✔✔jobsite
a stove unit without insulation must be how many inches away from
combustible material? - 🧠ANSWER ✔✔6"
a tee-wye is a - 🧠ANSWER ✔✔plumbing fitting
when screw are used instead of nails. the required spacing between
screws is usually - 🧠ANSWER ✔✔larger
where is a 4-prong outlet plug used - 🧠ANSWER ✔✔at the service to house