TYPICAL PROJECT" MODULE 7 QUESTIONS WITH
CORRECT ANSWERS 2025
What stage:
Gather available data
Prior to occupying TTC zone
Consider the needs of all users
Coordinate between adjacent or overlapping projects - CORRECT ANSWER -Planning
What stage:
Select best traffic control alternative
based on: safety, mobility, cost, constructability - CORRECT ANSWER -Design
What Factors effect the design of a TTC plan - CORRECT ANSWER -
Traffic Factors, characteristics, and speed.
Traffic controls, urban features, and traffic generators
What are the MUTCD categories of Work Duration? - CORRECT ANSWER -Long-term stationary
Intermediate-term stationary
short-term stationary
short-duration
mobile
Long-term stationary (MUTCD work duration category) - CORRECT ANSWER -
Occupies location more than 3 days
larger channelizing devices and post mounted signs
conflicting roadway markings removed and replaced with temporary markings
cover or remove conflicting signage