Newest 2025/2026 Complete Questions And Correct
Detailed Answers (Verified Answers) |Brand New Version!!
Project management is not limited to the __________ sector.
a. private
b. international
c. universal
d. business and government
e. global - ans -a. private
Which of the following represents the correct order of stages within the project
life cycle?
a. Defining, Planning, Executing, Closing
b. Planning, Defining, Closing, Executing
c. Executing, Defining, Planning, Closing
d. Planning, Defining, Executing, Closing
e. Closing, Planning, Defining, Executing
- ans -a. Defining, Planning, Executing, Closing
A project life cycle
a. must be dogmatically followed.
b. will always have a phase called 'visioning'.
c. reduces the amount of planning necessary.
d. can vary based on the industry.
e. will only ever consist of four phases.
- ans -d. can vary based on the industry.
Which of these is NOT part of the "sociocultural dimension" of project
management?
a. Managing customer expectations
b. Leadership
,c. Resource allocation
d. Dealing with politics
e. Negotiation - ans -c. Resource allocation
Any project life cycle is made up of stages. The project's schedule and budget will
be determined in the ___________ stage of the project life cycle.
a. planning
b. defining
c. executing
d. closing
e. conceptual - ans -a. planning
Training the customer, releasing staff and resources occurs in the ________ stage
of project life cycle.
a. defining
b. planning
c. conceptual
d. closing
e. executing - ans -d. closing
A series of coordinated, related, multiple projects that continue over an extended
time period and are intended to achieve a goal is known as a
a. Campaign.
b. Strategy.
c. Venture.
d. Program.
e. Crusade. - ans -d. program
An increase in the complexity of projects, because projects typically include the
latest advances, can be the result of a growth in new __________.
a. services
b. products and services
c. products
,d. processes
e. knowledge - ans -e. knowledge
Which of the following is NOT true about project management?
a. It is not limited to the private sector.
b. Many opportunities are available for individuals interested in this career path.
c. It focuses primarily on technical processes.
d. It is a set of tools.
e. It improves one's ability to plan, implement and manage activities to
accomplish specific organizational objectives
- ans -c. It focuses primarily on technical processes
In which stage of the project life cycle is the project's schedule and budget
determined?
a. Closing
b. Identifying
c. Planning
d. Defining
e. Executing - ans -c. planning
A project does not include
a. repetitive, same or similar work.
b. unique elements.
c. creating a new product or service.
d. a specific objective.
e. developing a new process.
- ans -a. repetitive, same or similar work
Project management is ideally suited for a business environment requiring all of
the following EXCEPT
a. Repeatability.
b. Accountability.
c. Innovation.
, d. Flexibility.
e. Speed. - ans -a. repeatability
Which of the choices listed below is NOT considered to be a characteristic of a
project?
a. For internal use only
b. An established objective
c. Specific time, cost and performance requirements
d. A clear beginning and end
e. Something never been done by a particular company before
- ans -a. for internal use only
On a project network, the activity times are derived from the
a. work packages.
b. project proposal.
c. budget.
d. responsibility matrix.
e. organization breakdown structure
- ans -a. work packages.
A(n) ________ is the minimum amount of time a dependent activity must be
delayed to begin or end.
a. lag
b. wane
c. saunter
d. lead
e. hobble - ans -a. lag
Consider the following table of activities A through G in which A is the start node
and G is the stop node.
On a piece of scratch paper, draw the network associated with this table and
determine the following. What is the late start time for activity E (how late can
activity E start?)? - ans -