" Material requirements planning (MRP) system nervousness can be attributed to
which of the following? - Correct answer-I. Unplanned demand II. MRP parameter
errors
"Which of the following are prerequisites to implementing a master production
scheduling system? - Correct answer-I. Define master production schedule (MPS)
unit III. Train an employee in MPS concepts and techniques"
"The master production schedule (MPS) translates the sales and operations plan
(SOP) into" - Correct answer-specific production plan
" The master production schedule (MPS) shows when products will physically be
available to ship." - Correct answer-false
The master production schedule is - Correct answer-neither a statement of current
production or current demand
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
, "The master production schedule (MPS) differs from the forecast by considering -
Correct answer-I. Capacity limits II. Production costs III. The sales and operations
plan (SOP"
" The master production schedule (MPS) must be stated in terms that relate to a
pro-ducible product." - Correct answer-true
" The master production schedule (MPS) must be stated in terms of actual
products." - Correct answer-false
" In which environment is a planning bill of materials most likely to be used?" -
Correct answer-assemble to order
"The master production schedule (MPS) considers preferred lot sizes when
construct-ing the plan" - Correct answer-true
13. cycle stock is - Correct answer-inventory carried as a result of lot size
requirements
"Available-to-promise (ATP) is likely to be least useful in which environment?" -
Correct answer-make to stock
"Which formula is used to calculate the projected available inventory balance?" -
Correct answer-Projected available inventory = Previous available inventory +
Master production schedule - MAX(Forecast, Actual orders)"
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
2026 Questions and Answers
" Material requirements planning (MRP) system nervousness can be attributed to
which of the following? - Correct answer-I. Unplanned demand II. MRP parameter
errors
"Which of the following are prerequisites to implementing a master production
scheduling system? - Correct answer-I. Define master production schedule (MPS)
unit III. Train an employee in MPS concepts and techniques"
"The master production schedule (MPS) translates the sales and operations plan
(SOP) into" - Correct answer-specific production plan
" The master production schedule (MPS) shows when products will physically be
available to ship." - Correct answer-false
The master production schedule is - Correct answer-neither a statement of current
production or current demand
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
, "The master production schedule (MPS) differs from the forecast by considering -
Correct answer-I. Capacity limits II. Production costs III. The sales and operations
plan (SOP"
" The master production schedule (MPS) must be stated in terms that relate to a
pro-ducible product." - Correct answer-true
" The master production schedule (MPS) must be stated in terms of actual
products." - Correct answer-false
" In which environment is a planning bill of materials most likely to be used?" -
Correct answer-assemble to order
"The master production schedule (MPS) considers preferred lot sizes when
construct-ing the plan" - Correct answer-true
13. cycle stock is - Correct answer-inventory carried as a result of lot size
requirements
"Available-to-promise (ATP) is likely to be least useful in which environment?" -
Correct answer-make to stock
"Which formula is used to calculate the projected available inventory balance?" -
Correct answer-Projected available inventory = Previous available inventory +
Master production schedule - MAX(Forecast, Actual orders)"