ACI GRADE 1 WRITTEN EXAM LATEST ACTUAL EXAM 200 QUESTIONS AND CORRECT DETAILED ANSWERS

Rating
-
Sold
2
Pages
5
Grade
A+
Uploaded on
14-09-2025
Written in
2025/2026

ACI GRADE 1 WRITTEN EXAM LATEST ACTUAL EXAM 200 QUESTIONS AND CORRECT DETAILED ANSWERS

Institution
ACI GRADE 1
Course
ACI GRADE 1









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ACI GRADE 1
Course
ACI GRADE 1

Document information

Uploaded on
September 14, 2025
Number of pages
5
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ACI GRADE 1 WRITTEN EXAM LATEST 2023-2024 ACTUAL EXAM 200 QUESTIONS AND CORRECT DETAILED
ANSWERS

The temp. measuring device shall be capable of accurately measuring the temp. of freshly mixed
concrete to ____ throughout a range of ____. - (answer) 1 Degree F, 30-120 Degrees F



A composite sample of concrete is required even if the only purpose for obtaining the sample is to
determine the temp. T or F? - (answer) False



C172/C172M covers sampling from five type of equipment which are___, ___, ___, ___, & ____? -
(answer) revolving drum, stationary, paving, continuous, & open top



The mold for making the slump test is in the shape of ____. - (answer) the frustum of a cone



The surface on which the slump mold will be placed must be ____. - (answer) Flat, moist non-
absorbent, & rigid



How deep should the tamping rod penetrate each layer? - (answer) Rod each layer throughout it's
depth , on second & final layer the rod should penetrate into the previous layer approximately 1 in.



Prior to lifting the mold, concrete must be removed from ____. - (answer) the area surrounding the
base of the mold



What is the minimum frequency of the vibrator used in Test Method C138/C138M - (answer) 9000
Vibrations/Min., 150 Hertz



What is the minimum thickness of a metal strike-off plate used in Test Method C138/C138M? -
(answer) 1/4 in.



What is the minimum thickness of a glass/acrylic strike-off plate used in Test Method C138/C138M? -
(answer) 1/2 in.



Measures other than air meter bowls used for Test Method C138/C138M must conform to Test Method
___. - (answer) C29/C29M

, ACI GRADE 1 WRITTEN EXAM LATEST 2023-2024 ACTUAL EXAM 200 QUESTIONS AND CORRECT DETAILED
ANSWERS



Air meter bowls used for Test Method C138/C138M must conform to Test Method ___ and be calibrated
for volume according to Test Method ___. - (answer) C231, C29



The pressure method of determining air content can be used on concrete containing ___ ____
aggregate. - (answer) relatively dense



The pressure method of determining air content cannot be used on concrete containing the following
types of aggregate: ___, ___, & ___. - (answer) light weight, air-cooled blast furnace slag, & aggregate
of high porosity



What is the minimum allowable capacity of the measuring bowl used in Test Method C231/C231M? -
(answer) 6L (0.2ft^3)



What are the required characteristics of the tamping rod used in Test Method C231/C231M? - (answer)
Round, straight steel rod, w/ a 16 mm (5/8 in) +-2 mm (1/16 in) diameter, length of at least 100 mm (4
in) greater than the depth of the measuring bowl, but not greater than 600 mm (24 in) in overall length
w/ the tamping end rounded to a hemispherical tip of the same diameter as the rod



What is the specified size of the mallet required for Test Method C231/C231M when the measuring
bowl has a capacity of 14 L (0.5 ft^3) or less? - (answer) 1 & 1/4 lbs +-0.5 lbs



The maximum size aggregate allowed for Test Method C231/C231M is ___. - (answer) 2 in



What tools maybe used to strike off the top surface of the concrete following consolidation of the final
layer? - (answer) strike-off plate made of acrylic, glass, or metal



What are the requirements of the strike off bar used in Test Method C173/C173M? - (answer) Flat
straight steel bar at least 3 x 20 x 300 mm (1/8 x 3/4 x 12 in) or a flat straight high density polyethyline
bar, or plastic of equal or greater abrasion resistance at least 6 x 20 x 300 mm (1/4 x 3/4 x 12 in)



In Test Method C173/C173M, When filling the measuring bowl of the air meter, the concrete must be
placed in _____ layers of equal volume. - (answer) 2
$17.99
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Testmister

Also available in package deal

Thumbnail
Package deal
Ultimate 500-Exam Mega Prep Bundle | All-in-One Test Bank with Verified Answers
-
500 2026
$ 513.33 More info

Get to know the seller

Seller avatar
Testmister Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
2601
Member since
1 year
Number of followers
0
Documents
1080
Last sold
1 week ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions