Which of the following are part of the shutdown procedure?
(Select all that
apply.) - ANSWER-Dispenser operating valves
are closed.
Transfer hoses are
secured.
Dispenser cabinet is
locked.
Tank valves are closed.
When filling by volume the meter register is used to
determine when the
cylinder is full of liquid propane. -
ANSWER-False
, Gloves and other PPE are required when filling containers
because of the ______ of liquid propane. - ANSWER-
refrigerating effect (potential for freeze burns)
Before filling a cylinder, verify that it is a propane cylinder by
___________. - ANSWER-reviewing the cylinder design code
specification markings on the cylinder
How many times do you need to complete the purging
process? - ANSWER-5
If a nozzle with a threaded connection is being used, it must be
firmly attached and properly threaded before beginning the any
filling process. - ANSWER-True
How far from the propane dispenser do you need to evacuate in
the event of an
uncontrolled release? -
ANSWER-330 ft
New cylinders that have NOT been vacuum-purged by the
manufacturer and cylinders that have been opened to the
atmosphere must be _______ prior to filling. - ANSWER-purged
of air or moisture