1. What is the primary purpose of a governor in a hydroelectric turbine
system?
A. Increase voltage output
B. Regulate turbine speed
C. Control water temperature
D. Protect the generator from overload
The governor maintains constant turbine speed by adjusting the flow
of water, ensuring frequency stability in the power output.
2. Which component converts mechanical energy into electrical energy
in a hydroelectric plant?
A. Penstock
B. Draft tube
C. Generator
D. Turbine
The generator is driven by the turbine and is responsible for
converting rotational mechanical energy into electricity.
,3. What is the function of a penstock?
A. Houses the generator
B. Controls turbine speed
C. Stores excess water
D. Delivers water to the turbine under pressure
The penstock is a pipe that directs pressurized water from the
reservoir to the turbine.
4. A Kaplan turbine is best suited for:
A. Low head and high flow conditions
B. High head and low flow conditions
C. Medium head and variable flow
D. Constant pressure applications
Kaplan turbines are adjustable propeller-type turbines ideal for sites
with low head and high water flow.
5. What device protects the generator from electrical faults?
A. Penstock
B. Governor
C. Exciter
D. Circuit breaker
Circuit breakers isolate the generator from the grid during faults to
prevent equipment damage.
6. What is cavitation in a hydro turbine?
A. Electrical short in the stator
B. Formation of vapor bubbles in flowing water
C. Excessive generator vibration
D. Loss of water flow
Cavitation causes pitting and damage to turbine blades due to vapor
bubble collapse under pressure.
, 7. Which of the following is a preventive maintenance task?
A. Replacing a failed generator
B. Lubricating turbine bearings
C. Resetting tripped relays
D. Responding to alarms
Preventive maintenance includes regular tasks like lubrication to
avoid future failures.
8. What is the typical frequency of electrical output in the U.S.?
A. 25 Hz
B. 100 Hz
C. 60 Hz
D. 50 Hz
Hydroelectric generators in the U.S. are synchronized to the standard
60 Hz frequency.
9. Which part of a hydro plant stores potential energy?
A. Reservoir
B. Turbine
C. Transformer
D. Draft tube
The reservoir holds water at a height, storing potential energy that
can be converted to kinetic energy.
10. What is the primary cause of generator overheating?
A. Low water flow
B. High turbine RPM
C. Overloading
D. Cold ambient temperatures
Overloading the generator beyond its rated capacity can cause
excessive heat buildup.