*#* A project's total site area is 280,000 SF (26,000 m2). The total previously
developed area on site is 100,000 SF (9,290 m2). The building FAR is 1.7. How
much financial support would an owner have to provide to ear SS credit Site
Development - Protect or Restore Habitat?
A) $112,000
B) $72,000
C) $122,400
D) $40,000 - 🧠 ANSWER ✔✔A) $112,000
,*Feedback:*
This type of question will likely include additional, extraneous information to
cause confusion. For Option 2 Financial Support, the requirement is as follows:
$0.40/SF ($4/m2) for the total site area including the building footprint.
280,000 X $0.40 = $112,000
*#* Which *non-mandatory* steps could a project team take prior to conducting
air-quality testing that would *improve* the test results for EQ Credit IAQ
Assessment? (Choose 2)
A) Vacuum using a vacuum cleaner with filtration media.
B) Test and balance the HVAC system
C) Install finishes and furniture
D) Clean with low-emitting cleaning products
E) Complete punch-list items that would generate VOCs or other contaminants. - 🧠
ANSWER ✔✔A) Vacuum using a vacuum cleaner with filtration media.
, 3
D) Clean with low-emitting cleaning products
*Notes:*
Here are the required steps before a flush-out or air testing:
Install all finishes and furniture
For residential projects, install owner-provided furniture
Complete punch-list items that would generate VOCs or other contaminants
Test and balance the HVAC system
*#* A project team has hired a LEED consultant to assist them with their first
LEED project. What will the consultant need to tell the project team to take
photographs of if they choose to pursue those credits?
A) SS Credit Rainwater Management
B) EQ Credit Construction IAQ Management Plan
C) LT Credit Surrounding Density and Diverse Uses
D) LT Credit Access to Quality Transit - 🧠 ANSWER ✔✔B) EQ Credit
Construction IAQ Management Plan
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
PRIVACY STATEMENT. ALL RIGHTS RESERVED
, Feedback:
Construction Management IAQ Management Plan requires photos that highlight
the implemented construction IAQ practices.
LT Credit Surrounding Density and Diverse Uses does not require a photo, but a
phot is one alternative for providing the site vicinity plan. Sketches, block
diagrams, and maps can also be used.
LT Credit Access to Quality Transit does not require photos.
SS Credit Rainwater Management does not require a photo or drawing.
*#* A university housing project with 100 one-bedroom apartments has a baseline
parking capacity of 1 parking space/unit from the ITE handbook.
The project will earn 1 point under *LT Credit Surrounding Density AND Diverse
Uses* BUT NOT earn *LT Credit Access to Quality Transit*.