Which of the following may NOT file a stop payment notice on public
works?
A. The direct contractor.
B. A subcontractor.
C. Material supplier.
D. Surveyor. - Correct Answer - The direct contractor.
The Underground Service Alert color code for a sewer line is:
A. green.
B. blue.
C. purple.
D. orange. - Correct Answer - green.
Which of the following payroll taxes is withheld from employee wages?
A. Federal Unemployment Tax (FUTA)
, B. State Employment Training Tax (ETT)
C. State Unemployment Insurance (UI)
D. State Disability Insurance (SDI) - Correct Answer - State Disability
Insurance (SDI)
All contractors working on a public works project MUST employ
apprentices on the project in each classification the contractor uses.
What percentage of every contractor's man hours come from
apprentices?
A. 30%
B. 25%
C. 20%
D. 15% - Correct Answer - 20%
Latent defects are:
A. illegal contracts
B. the owner's responsibility
C. the lender's responsibility
, D. Hidden defects that may take much time to discover and can be
costly. - Correct Answer - Hidden defects that may take much time
to discover and can be costly.
On a public works project if the subcontractor's percentage of the total
bid exceeds ______ the prime contractor must included the
subcontractor's name and address in the bid.
A. 0.5%
B. 2%
C. 5%
D. 10% - Correct Answer - 0.5%
For which of the following types of construction contracts does the
Business and Professions Code Section 7165 allow substitute
provisions, if the job is to be financed by a third party lender?
A. roofing job
B. landscaping job
C. swimming pool job
D. heating and air conditioning job - Correct Answer - swimming pool
job
Who of the following may require the contractor to obtain a performance
and payment bond?
, A. liability insurer
B. tenant
C. subcontractor
D. Contractors State License Board - Correct Answer - tenant
If you are working on a difficult phase of a project and the owner comes
to you with a complaint about the windows you have installed, what do
you do?
A. Acknowledge the complaint and tell the owner you will be right with
him as soon as possible.
B. Stop what you are doing and deal with the owner's complaint.
C. Have your foreman handle the complaint.
D. Turn the complaint over to the Contractor's Board. - Correct
Answer - Stop what you are doing and deal with the owner's
complaint.
Contractors must hire apprentices if the public works contract is valued
at _________ or more.
A. $25,000
B. $30,000
C. $50,000
and Answers Rated A+ | 100% Correct |
Latest 2025/2026 Guide
Which of the following may NOT file a stop payment notice on public
works?
A. The direct contractor.
B. A subcontractor.
C. Material supplier.
D. Surveyor. - Correct Answer - The direct contractor.
The Underground Service Alert color code for a sewer line is:
A. green.
B. blue.
C. purple.
D. orange. - Correct Answer - green.
Which of the following payroll taxes is withheld from employee wages?
A. Federal Unemployment Tax (FUTA)
, B. State Employment Training Tax (ETT)
C. State Unemployment Insurance (UI)
D. State Disability Insurance (SDI) - Correct Answer - State Disability
Insurance (SDI)
All contractors working on a public works project MUST employ
apprentices on the project in each classification the contractor uses.
What percentage of every contractor's man hours come from
apprentices?
A. 30%
B. 25%
C. 20%
D. 15% - Correct Answer - 20%
Latent defects are:
A. illegal contracts
B. the owner's responsibility
C. the lender's responsibility
, D. Hidden defects that may take much time to discover and can be
costly. - Correct Answer - Hidden defects that may take much time
to discover and can be costly.
On a public works project if the subcontractor's percentage of the total
bid exceeds ______ the prime contractor must included the
subcontractor's name and address in the bid.
A. 0.5%
B. 2%
C. 5%
D. 10% - Correct Answer - 0.5%
For which of the following types of construction contracts does the
Business and Professions Code Section 7165 allow substitute
provisions, if the job is to be financed by a third party lender?
A. roofing job
B. landscaping job
C. swimming pool job
D. heating and air conditioning job - Correct Answer - swimming pool
job
Who of the following may require the contractor to obtain a performance
and payment bond?
, A. liability insurer
B. tenant
C. subcontractor
D. Contractors State License Board - Correct Answer - tenant
If you are working on a difficult phase of a project and the owner comes
to you with a complaint about the windows you have installed, what do
you do?
A. Acknowledge the complaint and tell the owner you will be right with
him as soon as possible.
B. Stop what you are doing and deal with the owner's complaint.
C. Have your foreman handle the complaint.
D. Turn the complaint over to the Contractor's Board. - Correct
Answer - Stop what you are doing and deal with the owner's
complaint.
Contractors must hire apprentices if the public works contract is valued
at _________ or more.
A. $25,000
B. $30,000
C. $50,000