LEVEL 2
Save
Terms in this set (82)
1. Supplemental Three ways to modify contract documents after
Agreement execution
2. Work order
3. Unilateral Payment
Special Provision Order of document precedence
Technical Special
Provision
Plans
Standard plans
Developmental
Specifications
Supplemental
Specifications
Standard Specifications
for Road bridge
Monthly progress Contractor's monthly payment is based on?
estimates
,1. Percent of allowable When is retainage withheld?
contract used exceeds
75%
AND
Difference in percentage
of contract time used
exceeds the percentage
of contract amount
earned by more than 15%
1. Supplemental Three ways to modify contract documents
Agreement
2. Work order
3 unilateral payment
Initial contingency Work orders are funded through:
amount (999-25-XX)
Contingency
supplemental agreement
(CSA), which can't be
issued until at least 50%
of initial contingency
amount pay item funds
are expended
Disagreement between What is an unilateral payment?
dept and contractor on
terms or contractor fails
to timely execute a WO
or SA
Liqudated Damages can be refunded on monthly
True
progress estimate?
Calculate error in plan quantity
, A. Difference between What is error in lump sum
the original plan quantity quantity?
and final quantity of more
than 5%
OR
B. A change in quantity
that results in a change
amount payable of more
than $5k
Strike through, initial, How to make correction in field book?
date
Pay item quantities need to be documented with 30
TRUE
days of field completion
What's the amount overruns/underruns need to be
+/- $10,000
explained?
When "Asphalt Base When should bituminous adjustments be applied?
Only" is specified in the
plans under the typical
section and when
minimum criteria for
contracts are met
1. The pay quantity paced Adjustments to Misc Asphalt include:
on the project, limited to
105% of the adjusted PQ
2. Fuel Adjustments
3. Bituminous
Adjustments
(CPF-1) x unit price How to calculate CPF Adjustments?
Independent test What is a resolution test?
performed when QC and
VT samples do not
compare.
At an independent lab Where is resolution test accomplished?