2025 PMP Exam Prep Mastery: 65 Comprehensive Multiple Choice Questions and Expert Rationales for Chapters 6 to 9 – Schedule, Cost, Quality, and Resource Management

Institution
2025 PMP
Course
2025 PMP











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
2025 PMP
Course
2025 PMP

Document information

Uploaded on
May 20, 2025
Number of pages
31
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

2025 PMP Exam Prep Mastery: 65 Comprehensive
Multiple Choice Questions and Expert Rationales
for Chapters 6 to 9 – Schedule, Cost, Quality, and
Resource Management


To control the schedule, a project manager is reanalyzing the project to predict project
duration. She does this by analyzing the sequence of activities with the lease amount of
scheduling flexibility. What technique is she using?

A: Critical path method

B: Flowchart

C: Procedure diagramming

D: Work breakdown structure - - correct ans- -Critical path method



There are only two choices related to scheduling: critical path method and procedure
diagramming. Precedence diagramming, however, is a diagramming technique that
deals with the relationship between activities, not schedule flexibility. The project
manager is analyzing the critical path.



A dependency requiring that design be completed before manufacturing can start is an
example of a(n):

A: Discretionary dependency

B: External dependency

C: Mandatory dependency

D: Scope dependency - - correct ans- -Mandatory dependency



No mention is made that the dependency comes from a source outside the project, so
this is not an external dependency. Scope dependency is not a defined term. The key
word in the question is "requiring". Since the dependency is required, it could not be

,discretionary and therefore must be mandatory. The question defines a mandatory
dependency.



Which of the following are GENERALLY illustrated BETTER by bar charts than network
diagrams?

A: Logical relationships

B: Critical paths

C: Resource trade-offs

D: Progress or status - - correct ans- -Progress or status



The bar chart (or Gantt chart) is designed to show a relationship to time. This is best
used when demonstrating progress or status as a factor of time.



If the optimistic estimate of an activity is 12 days, and the pessimistic estimate is 18
days, what is the standard deviation of this activity?

A: 1

B: 1.3

C: 6

D: 3 - - correct ans- -1



The beta standard deviation is computed by (P-O)/6. Therefore, the answer is (18-
12)/6=6/6=1.



A heuristic is BEST described as a:

A: Control tool

B: Scheduling method

C: Planning tool

D: Generally accepted rule - - correct ans- -Generally accepted rule

,A heuristic is a generally accepted rule. Examples are cost per line of code, cost per
square foot of floor space, etc.



Lag means:

A: The amount of time an activity can be delayed without delaying the product finish
date.

B: The amount of time an activity can be delayed without delaying the early start date of
its successor.

C: Waiting time.

D: The product of a forward and backward pass. - - correct ans- -Waiting time



Total float and free float are the time an activity can be delayed without impacting the
entire project or the next activity. A forward or back ward pass refers to a network
analysis technique, not waiting time. Waiting time is the correct definition of lag.



Which of the following is the BEST project management tool to use to determine the
longest time the project will take?

A: Work breakdown structure

B: Network diagram

C: Bar chart

D: Project charter - - correct ans- -Bar Chart



The bar chart may show an end date, but it is not used to determine dates. The project
charter also may include a required end date, but not a logical determination of how
long the project will take. The network diagram takes the activities from the activity list
and adds dependencies. The dependencies allow us to look at the various paths
through the diagram to determine the longest duration (critical) path. The network
diagram is the best answer.



Which of the following is CORRECT?

A: The critical path helps prove how long the project will take.

, B: There can be only one critical path.

C: The network diagram will change very time the end date changes.

D: A project can never have negative float. - - correct ans- -The critical path helps prove
how long the project will take



This question tests your knowledge about a number of topics. There can often be more
than one critical path. The network diagram may or may not change when the end date
changes, depending on the amount of schedule reserve and the reason for the change
to the schedule. You can have negative float if you are behind schedule. The critical path
helps prove how long the project will take. This is the only correct statement of the
choices given.



What is the duration of a milestone?

A: It is shorter than the duration of the longest activity.

B: It is shorter than the activity it represents.

C: It has no duration.

D: It is the same length as the activity it represents. - - correct ans- -It has no duration



A milestone represents the completion of a series of activities or work packages.
Therefore, it takes no time of its own.



Which of the following BEST describes the relationship between standard deviation and
risk?

A: There is not relationship.

B: Standard deviation tells you if the estimate is accurate.

C: Standard deviation tells you how uncertain the estimate is.

D: Standard deviation tells you if the estimate includes a pad. - - correct ans- -Standard
deviation tells you how uncertain the estimate is



An estimate can have a wide range and still be accurate if the item estimated includes
identified risks. There is no such thing as a pad in proper project management. An

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
premiumessay WGU
View profile
Follow You need to be logged in order to follow users or courses
Sold
82
Member since
3 year
Number of followers
70
Documents
667
Last sold
2 months ago

4.9

114 reviews

5
107
4
4
3
0
2
2
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions