100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Construction FE Civil Exam Questions and Answers 100% Pass

Rating
-
Sold
-
Pages
22
Grade
A+
Uploaded on
25-03-2025
Written in
2024/2025

Construction FE Civil Exam Questions and Answers 100% Pass Is the most traditional project delivery method and appeals to those looking for low- cost bids. In this method, the owner contracts designers and builders separately. - Design-bid-build is a construction project delivery method where the designer and builder work together under a single contract from the beginning of the project in order to ensure unity and collaboration throughout the process. - Design- build Select all that clearly demonstrate an advantage of the Design-Build project delivery over the Design-Bid-Build approach: - There is single point of contractual responsibility for the owner for the entire project -There are contractual relationships with the Owner that prevent a conflict of interest -The design is clearly and explicitly defined at the outset of the project - The design includes significant collaboration between the Engineer and the Contractor -The schedule can be fast-tracked and construction can begin before the complete project design is finalized - The Owner will receive a project at the lowest competitive cost - There is single point of contractual responsibility for the owner for the entire project 2© EMILY CHARLENE YEAR , ALL RIGHTS RESERVED There is single point of contractual responsibility for the owner for the entire project The schedule can be fast-tracked and construction can begin before the complete project design is finalized An indemnification clause in an engineer's design contract is typically tied to: A. Negligent engineering design B. Claims submitted by parties affected by a failure C. Project cost overruns D. Improper construction methods by the Contractor - A. Negligent engineering design Collusion on a construction project typically refers to which of the fol

Show more Read less
Institution
FE Civil
Course
FE Civil










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
FE Civil
Course
FE Civil

Document information

Uploaded on
March 25, 2025
Number of pages
22
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Construction FE Civil Exam Questions
and Answers 100% Pass

Is the most traditional project delivery method and appeals to those looking for low-
cost bids. In this method, the owner contracts designers and builders separately. -
✔✔Design-bid-build

is a construction project delivery method where the designer and builder work together
under a single contract from the beginning of the project in order to ensure unity and
collaboration throughout the process. - ✔✔Design- build

Select all that clearly demonstrate an advantage of the Design-Build project delivery
over the Design-Bid-Build approach:




- There is single point of contractual responsibility for the owner for the entire project

-There are contractual relationships with the Owner that prevent a conflict of interest

-The design is clearly and explicitly defined at the outset of the project

- The design includes significant collaboration between the Engineer and the Contractor

-The schedule can be fast-tracked and construction can begin before the complete
project design is finalized

- The Owner will receive a project at the lowest competitive cost - ✔✔There is single
point of contractual responsibility for the owner for the entire project



© EMILY CHARLENE YEAR 2025-2026, ALL RIGHTS RESERVED 1

,There is single point of contractual responsibility for the owner for the entire project




The schedule can be fast-tracked and construction can begin before the complete project
design is finalized

An indemnification clause in an engineer's design contract is typically tied to:




A. Negligent engineering design

B. Claims submitted by parties affected by a failure

C. Project cost overruns

D. Improper construction methods by the Contractor - ✔✔A. Negligent engineering
design

Collusion on a construction project typically refers to which of the following?




A. A practice where multiple contractors conspire to fix prices or rig bids

B. A system where public officials receive money from the contractor after award

C. Falsely increasing the price of change order

D. Misrepresenting the amount of work that has been completed to get advance
payments - ✔✔A. A practice where multiple contractors conspire to fix prices or rig
bids

A preconstruction conference should be he held:




© EMILY CHARLENE YEAR 2025-2026, ALL RIGHTS RESERVED 2

, A. Prior to advertising for bids

B. After advertising for bids but before bids are received

C. After bid opening but before award of the contract

D. After execution of an agreement but before Notice to Proceed - ✔✔D. After execution
of an agreement but before Notice to Proceed

Types of submittals for engineer approval typically include all the following except:

A. Product data

B. Shop drawings

C. Installation means and methods

D. Mill certificates - ✔✔C. Installation means and methods

Which of the following statements best define what is meant by "substantial
completion" with respect to a construction contract?




A. Project can be used and occupied by the owner and is completely finished B. Project
can be used and occupied by the owner but there is still a punch-list of minor work
remaining

C. Contractor's performance bond will be used to finish the remaining work

D. The owner has received a final release of liens from all subcontractors - ✔✔B. Project
can be used and occupied by the owner but there is still a punch-list of minor work
remaining

a financial guarantee that the terms of a contract will be honored. If one party to a
contract cannot complete their obligations, the bond is paid out to the other party to
compensate for their damages or costs. - ✔✔Performance bond


© EMILY CHARLENE YEAR 2025-2026, ALL RIGHTS RESERVED 3

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
EmilyCharlene Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
442
Member since
2 year
Number of followers
139
Documents
21009
Last sold
1 day ago
Charlene\'s Scholastic Emporium.

Your Actual and Virtual Exam Tests Excellent Tutor.

3.6

96 reviews

5
44
4
13
3
15
2
7
1
17

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions