Change Directive - CORRECT ANSWER - A written instruction prepared by the
Consultant and signed by the Owner directing the Contractor to proceed with a change in the
Work within the general scope of the Contract Documents prior to the Owner and the Contractor
agreeing upon adjustments in the Contract Price and the Contract Time.
Change Order - CORRECT ANSWER - A written amendment to the Contract prepared by
the Consultant and signed by the Owner and the Contractor stating their agreement upon:
- a change in the Work;
- the method of adjustment or the amount of the adjustment in the Contract Price, if any; and
- the extent of the adjustment in the Contract Time, if any.
Construction Equipment - CORRECT ANSWER - All machinery and equipment, either
operated or not operated, that is required for preparing, fabricating, conveying, erecting, or
otherwise performing the Work but is not incorporated into the Work.
Consultant - CORRECT ANSWER - The person or entity engaged by the Owner and
identified as such in the Agreement.
The Consultant is the Architect, the Engineer or entity licensed to practice in the province or
territory of the Place of the Work. The term Consultant means the Consultant or the Consultant's
authorized representative.
Contract - CORRECT ANSWER - The undertaking by the parties to perform their
respective duties, responsibilities and obligations as prescribed in the Contract Documents and
represents the entire agreement between the parties.
Contract Documents - CORRECT ANSWER - Consists of those documents listed in the
Agreement - CONTRACT DOCUMENTS and amendments agreed upon between the parties