100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Con 367 Midterm 2 Questions With Answers

Rating
-
Sold
-
Pages
11
Grade
A+
Uploaded on
11-01-2025
Written in
2024/2025

Con 367 Midterm 2 Questions With Answers...

Institution
Con 367
Course
Con 367









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Con 367
Course
Con 367

Document information

Uploaded on
January 11, 2025
Number of pages
11
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • con 367 midterm 2

Content preview

Con 367 Midterm 2 Questions With
Answers

True/ False

The dollar amount shown for each line item in a Schedule of Values reflects
the direct cost for that line item only and does not include the profit and
overhead. - ANSWER False

Which of the following is not in the To-Do list for the Facilitator in a
Meeting?

-Empower the attendees to communicate their ideas only if they agree with
you.

-Have an agenda and distribute it to the attendees well in advance of the
meeting.

- Know what you want to accomplish.

-Communicate action items at the conclusion of the meeting. - ANSWER
Empower the attendees to communicate their ideas only if they agree with
you.

Which of the following is not the responsibility of the Designer?

-Generate the shop drawings in a timely manner.

-Review the RFIs and respond to them in a timely manner.

-Consult with the Resident Project Representative in evaluating the RFIs.

, -Avoid directing or controlling the Contractor's means and methods. -
ANSWER Generate the shop drawings in a timely manner.

True/ False

Preconstruction meeting is typically held after the construction operations
begin. - ANSWER False

True/ False

Builder's Risk Insurance is typically purchased by the Designer. - ANSWER
False

Which of the following is not a characteristic of Schedule of Values (SOV)?

-It should be prepared by the Contractor and submitted to the Owner at the
end of the project.

-Line items in the SOV are typically determined by the Owner.

-The greater the detail in the SOV, the more accurate the estimate for the
progress payments.

-The Contractor must prorate overhead and profit on the line items in the
SOV. - ANSWER It should be prepared by the Contractor and submitted to
the Owner at the end of the project.

In the tripartite relationship inherent in construction bonding between the
Owner, Contractor, and Surety, which one is the Obligee? - ANSWER Owner

True/ False

According to the negotiation method discussed in class (Getting to Yes), one
thing that needs to be done during negotiations is not to attack each other
but to attack the problem. - ANSWER True

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Newsolution Chamberlain College Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
298
Member since
4 year
Number of followers
196
Documents
2583
Last sold
4 days ago

3.9

58 reviews

5
30
4
10
3
8
2
3
1
7

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions