100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

WGU C722 Project Management: Test 2 for Exam Preparation

Rating
-
Sold
-
Pages
14
Grade
A+
Uploaded on
05-01-2025
Written in
2024/2025

WGU C722 Project Management: Test 2 for Exam Preparation

Institution
WGU C722
Course
WGU C722









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
WGU C722
Course
WGU C722

Document information

Uploaded on
January 5, 2025
Number of pages
14
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

WGU C722 Project Management: Test 2 for Exam Preparation

A manufacturing company is reviewing potential projects for the coming year based on the CEO's
request to reduce overhead costs. Which of the following projects would best align with the company's
desired business strategy? - correct answer ✔✔Replacing warehouse lighting with higher efficiency
bulbs and motion sensors



An office supply store is starting a project to provide a new service to their customers. Which of the
following strategic goals would be achieved by this project? - correct answer ✔✔Increasing the delivery
area served by existing locations



Which of the following would a firm establish to organize needed changes to support a long-term goal or
objective? - correct answer ✔✔Portfolio



Which of the following are project management organizations or standards commonly used by
companies to structure their project management processes? - correct answer ✔✔PMBOK

PRINCE@



Which organization oversees the PMP certification? - correct answer ✔✔PMI



Which of the following is a knowledge area of the PMBOK? - correct answer ✔✔Risk Management



Which of the following is the highest level of project management maturity for an organization according
to the OPM3? - correct answer ✔✔Sustained



What is an important benefit of a company establishing a PMO? - correct answer ✔✔Documents best
practices, lessons learned, and project costs



Documents best practices, lessons learned, and project costs - correct answer ✔✔Clarity regarding who
is in charge and who answers to whom

, A weak matrix organizational structure is most similar to which of the following? - correct answer
✔✔Departmental



A small company without a PMO is planning on only doing two projects next year and cannot afford to
hire a consultant. As they consider how to prioritize among several proposed projects, what is a criterion
that will drive the model used to select the top projects? - correct answer ✔✔Low cost



Executives at a small regional hospital are working to prioritize projects for the coming year. Due to
election-year discussions surrounding the future of several government healthcare programs, they are
worried about selecting a project that will become obsolete. What project selection model would help
them choose the best projects in spite of changing conditions? - correct answer ✔✔Flexible



A chain of grocery stores undertakes a project to replace card readers in their checkout lines with a new
technology consistent with current banking regulations and encryption standards since the old
technology is being phased out by their bank. What project selection model is being utilized in this
situation? - correct answer ✔✔Operating necessity



A newly established PMO asks management, employees, and project management staff to submit
questions to be used as criteria for prioritizing projects. They plan to use all submitted questions and
weight them based on how many people submit the same question. What type of project selection
model is being used? - correct answer ✔✔Checklist



A newly established PMO asks management, employees, and project management staff to submit
questions to be used as criteria for prioritizing projects. They plan to use all submitted questions and
weight them based on how many people submit the same question. What is the benefit of using this
approach? - correct answer ✔✔Project impact to all departments will be considered



Which of the following measures calculates the amount of time it should take to recoup the cost to
implement a project? - correct answer ✔✔Payback Period



While comparing proposed projects for next quarter, management tells the PMO not to worry about
how long it takes to earn back the cost of the selected projects but rather to focus on maximizing the
amount of money earned or saved over the long term. What numeric selection model is being used? -
correct answer ✔✔Return on Investment

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BravelRadon Havard School
View profile
Follow You need to be logged in order to follow users or courses
Sold
868
Member since
4 year
Number of followers
540
Documents
41036
Last sold
5 days ago
EXAM HUB

Welcome to Exam Hub Are you looking for high-quality, exam-ready notes, past papers, Test Banks, and well-researched study materials to boost your grades? You’re in the right place! I create and upload detailed, easy-to-understand, and well-structured documents across multiple subjects. All my materials are designed to help you study , save time, and excel in your coursework and exams! On this page NURSING EXAMS,STUDY GUIDES,TESTBANKS AND QUALITY EXAMS IS THE KEY TO STUDENTS CAREER EXCELLENCE, you find all documents, package deals, and flashcards offered by BravelRadon (EXAM HUB STORES!)....kindly recommend a friend for A+ GARANTEEd either you are a first-year student or final-year graduation! best of luck!

Read more Read less
3.5

153 reviews

5
55
4
30
3
32
2
8
1
28

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions