how many employees are you required to have in order to have works comp? -
ANSWER✅✅more than 1 employee
if you fail to identify and mark underground utilities, how much do you have to pay
for violation - ANSWER✅✅you can be fined up to 5000 dollars for the first violation,
and up to 70000 dollars
sets limits on how much of a air pollutant is allowed in the air. - ANSWER✅✅the
clean air act
when does the fair labor act apply - ANSWER✅✅it applies to employers that have 1
or more employee
, what is form I-9 - ANSWER✅✅this form is used by immigration ,to make sure
employees has legal immigration status in the usa
what is project over head - ANSWER✅✅items needed to complete the project ex;
bonds,temporary storage,dumpsters,security guards , porter potties,etc. makes up
5-10% of bid
what is the clean water act - ANSWER✅✅establishes the basic structure for
regulating disharges of pollutants into the waters of united states
what are current liabilities - ANSWER✅✅liabilities that will mature and must be
paid within 1 year
immigration forms must be kept for how long - ANSWER✅✅at least 3 years
what is a maintance bond - ANSWER✅✅guarantees that for one year no defective
workmanship or material will appear on completed project
liability insurance is what - ANSWER✅✅to protect 3rd party claims
keyman life insurance - ANSWER✅✅its to continue business if one dies or becomes
incapacitated
how much money is deducted from employee to pay for works comp -
ANSWER✅✅nothing. employer pays for everything
how soon must form I-9 be completed by - ANSWER✅✅it should be completed
within 3 days of hire
how long should you keep lead pamphlet receipt for - ANSWER✅✅must be kept for
3 years
bonds or cash deposits should be under whos name - ANSWER✅✅the licensee
how soon should you do a publication - ANSWER✅✅you must publish within 60
days for 3 consecutives publications
who certifies when a project is complete and the work meets conditions of the
contract documents - ANSWER✅✅the architect or the engineer
what are progress payments - ANSWER✅✅are partial payments made after
specified phases of construction are complete
what is the single prime method - ANSWER✅✅its when a project owner hires an
architectural firm to design the project the contractor then perfume the work