NCCCO - National Commission for the Certification of
Crane Operators
NCCCO Tower Crane Operator Certification Exam
Course Title and Number: NCCCO Tower Crane Operator
Certification Exam
Exam Title: Board Exam
Exam Date: Exam 2024- 2025
Instructor: [Insert Instructor’s Name]
Student Name: [Insert Student’s Name]
Student ID: [Insert Student ID]
Examination
180 minutes
Instructions:
1. Read each question carefully.
2. Answer all questions.
3. Use the provided answer sheet to mark your responses.
4. Ensure all answers are final before submitting the exam.
5. Please answer each question below and click Submit when you have
completed the Exam.
6. This test has a time limit, The test will save and submit automatically when the
time expires
7. This is Exam which will assess your knowledge on the course Learning
Resources.
Good Luck!
, For Inquiries🤔 about This or 📑Any Other Exam 📱HMU
📧
NCCCO - National Commission for the Certification of
Crane Operators 2024-2025
NCCCO Tower Crane Operator Certification Exam Prep
Study Guide Questions and Answers | 100% Pass
Guaranteed | Graded A+ |
Read All Instructions Carefully and Answer All the
Questions Correctly Good Luck: -
Where is the best location for leveling a crane? -
=Answer>> upper works
When determining the "gross load" the best method is:
- =Answer>> get an accurate load weight and add the
rigging
By order of hitch strength, which is the correct answer?
- =Answer>> basket, vertical, choker
What is the purpose of using a jib? - =Answer>>
increase height
Before crane erection can begin what must be
available? - =Answer>> Surface that is firm, drained
and graded
OSHA 29 CFR 1926.1407 Power Line Safety, Option 1
Requires what? - =Answer>> Power Lines are de-
energized and grouded
OSHA 29 CFR 1926.1407 Power Line Safety, Option 2
Requires what? - =Answer>> 20 Foot Clearance
OSHA 29 CFR 1926.1407 Power Line Safety, Option 3
Requires what? - =Answer>> Table Clearance
Need Writing 📝Help? We've Got You Covered! ✍️
100% NO A I or Plagiarism Guaranteed🎯
💬 Chat with us here: 📧
, For Inquiries🤔 about This or 📑Any Other Exam 📱HMU
📧
Before work can began for a new erected tower carne
what must be done before crane can begin working? -
=Answer>> Set load motion limits and safety devices
What type of attachment system is used to hold a
personnel platform to the crane hook - =Answer>>
Master link attachment or safety type shackle
When should a personnel platform be used -
=Answer>> there is no other safe way to perform the
task
OSHA, Cranes and Derricks working in Construction is
under what regulation - =Answer>> 29 CFR 1926
What is the safety Factor of suspended platform and
shackles - =Answer>> 10 to 1
What ASME Standard applies to personnel platforms -
=Answer>> B 30.23
Annual inspection records must be kept for how long -
=Answer>> 12 months
What ASME Standard applies to Tower Cranes -
=Answer>> B 30.3
Expendable tower base, the tolerance for "plumb" is? -
=Answer>> 1/4 - 10ft
Free standing Hammerhead tower crane mast will be
"plumbed" to a tolerance of; - =Answer>> 1 inch =
40ft
Before crane components are erected they shall be -
=Answer>> Visually inspected for damage from
shipping and handling
Need Writing 📝Help? We've Got You Covered! ✍️
100% NO A I or Plagiarism Guaranteed🎯
💬 Chat with us here: 📧
, For Inquiries🤔 about This or 📑Any Other Exam 📱HMU
📧
Where would the insulating link device be attached -
=Answer>> Attached or installed at the end of load
line and the load
annual/comprehensive inspection must include the
qualified person to perform - =Answer>> functional
motion testing of the equipment
rail buffers or rail stops must be placed how far from
the end of the travel tracks - =Answer>> 3 ft
Internal climbing crane must be plumbed by using what
to hold the crane in position - =Answer>> Wedges
What is the maximum rate of wind speed allowed to
climb a tower crane - =Answer>> 20 mph
During erection or dismantling operations, who must
always be present - =Answer>> AD director
How many wraps shall remain on the hoist drum
according to the Tower Crane Reference Manual -
=Answer>> 3
Personnel Platform must be Proof Tested each day
before use, how much weight is sued and how long
must the test last for - =Answer>> 125% and hold for
5 minutes
OSHA 1926. 1407 power requirements for 1000kv are -
=Answer>> Remain 20' or more from lines
Standing rope or pendant lines must have the following
minimum design factor of - =Answer>> 3:1