PSMI (True or False) Exam 100% Verified
True or False? The Sprint Goal is an outcome of Sprint Planning, so too the Sprint
Backlog. - ANSWER True
True or False: The Product Owner decides on how many of the Product Backlog items
the Development Team picks for a Sprint? - ANSWER False
True or False? Several Scrum Teams working on one project need to share the same
start date for a Sprint. - ANSWER True
True or False? The Product Owner ensures the team selects enough from the Product
Backlog for a Sprint to satisfy the stakeholders. - ANSWER False
True or false? Scrum has a role called "Project Manager"? - ANSWER False
True or false? The product backlog ist fixed and can not change. - ANSWER False
True or false? It is best to have Sprints of consistent length throughout a development
effort. - ANSWER True
True or false? A product Increment must be released to production at the end of each
Sprint. - ANSWER False
True or false? The Product Owner must release each increment to production -
ANSWER False
True or false? The development team selects the product owner. - ANSWER False
, True or False? A Scrum Team is only allowed to meet with stakeholders during the
Sprint Review? - ANSWER False
True or False? Every Scrum Team must have a Product Owner and Scrum Master? -
ANSWER True
True or False? Cross-functional teams are optimised to work on one technical layer of
the system only (eg. GUI, database, middle tier, interfaces). - ANSWER False
True or false? One product worked on by many teams requires each team to keep its
own Product Backlog. - ANSWER False
True or false? Scrum is a framework that describes in great detail how to make software
in incremental pieces. - ANSWER False
True or false? The Sprint is for the purpose of producing a done increment of the
Product. - ANSWER True
True or false? The product increment must be released to production at the end of each
Sprint. - ANSWER False
True or false? A Sprint is for producing a done increment of working product. - ANSWER
True
True or false? Sprints are never longer than a calendar month. - ANSWER True
True or False? Scrum Team and Development Team are the same. - ANSWER False
True or False? Sprints lengths can be different each Sprint as long as they don't exceed
a month. - ANSWER False
True or False? The Sprint Goal is an outcome of Sprint Planning, so too the Sprint
Backlog. - ANSWER True
True or False: The Product Owner decides on how many of the Product Backlog items
the Development Team picks for a Sprint? - ANSWER False
True or False? Several Scrum Teams working on one project need to share the same
start date for a Sprint. - ANSWER True
True or False? The Product Owner ensures the team selects enough from the Product
Backlog for a Sprint to satisfy the stakeholders. - ANSWER False
True or false? Scrum has a role called "Project Manager"? - ANSWER False
True or false? The product backlog ist fixed and can not change. - ANSWER False
True or false? It is best to have Sprints of consistent length throughout a development
effort. - ANSWER True
True or false? A product Increment must be released to production at the end of each
Sprint. - ANSWER False
True or false? The Product Owner must release each increment to production -
ANSWER False
True or false? The development team selects the product owner. - ANSWER False
, True or False? A Scrum Team is only allowed to meet with stakeholders during the
Sprint Review? - ANSWER False
True or False? Every Scrum Team must have a Product Owner and Scrum Master? -
ANSWER True
True or False? Cross-functional teams are optimised to work on one technical layer of
the system only (eg. GUI, database, middle tier, interfaces). - ANSWER False
True or false? One product worked on by many teams requires each team to keep its
own Product Backlog. - ANSWER False
True or false? Scrum is a framework that describes in great detail how to make software
in incremental pieces. - ANSWER False
True or false? The Sprint is for the purpose of producing a done increment of the
Product. - ANSWER True
True or false? The product increment must be released to production at the end of each
Sprint. - ANSWER False
True or false? A Sprint is for producing a done increment of working product. - ANSWER
True
True or false? Sprints are never longer than a calendar month. - ANSWER True
True or False? Scrum Team and Development Team are the same. - ANSWER False
True or False? Sprints lengths can be different each Sprint as long as they don't exceed
a month. - ANSWER False