Which of the following should a special inspector contact the
contractor about immediately?
A) If the concrete temperature is 80 degrees
B) If the slump calls for a maximum of 4' but is 6'
C) If the air content calls for 6% but is 3%
D) If the steel isn't tied properly - Answer-B and C
Can a material not listed in the IBC be used for construction?
A) Yes
B) No - Answer-A
Who should NOT hire the special inspector?
A) The building official
B) The contractor
C) The Owner
D) The RDP - Answer-B
,Who's job is it to ensure that the special inspector has an
approved set of plans?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-B
Who should the special inspector notify upon arrival to the
jobsite?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-B
A basic knowledge in which subject is NOT required to be a
special inspector?
A) Structural design
B) An understanding of construction documents
C) An understanding o the current codes
,D) How to perform all test expected of you - Answer-A)
Structural design
Who hires the special inspector?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-C and D
Who can deem special inspections unnecessary?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-A) The building official
Who performs a structural observation?
A) the RDP in responsible charge
B) The special inspector
C) The contractor
D) The building official - Answer-A) the RDP in responsible
charge
, Who prepares the statement of special inspections?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-D) The RDP
Who is in charge of reviewing and approving reports?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - Answer-D) The RDP
ICC exams are based on which document?
a) ACI
b) IBC
c) ASTM - Answer-B) IBC
Who is in charge of giving "approval to proceed"