WGU Project Management C783- Task 1 Initiating and Planning the Project











Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
October 4, 2024
Number of pages
16
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Task 1: Initiating and Planning the Project



Course: Financial Management for IT Professionals — C783
Date: 08/10/2024

,Initiating Process

A. Describe the initiating process for the data migration project, which uses
a traditional methodology, by doing the following:

1. Discuss the purpose of a project charter.
The purpose of a project charter is “so the project team knows why this
project matters, where the team is headed and what the project
objective is” (Project, 2017). There are project parameters that are
required to be adhered to and utilizing a project charter will keep the
team focus and within the project boundaries. Merrilton Robotics is
looking to migrate their data center functionality to the cloud. This
directive must be completed within six months with a maximum
budget of $2 million. The awarded Managed Service Provider (MSP)
must also store all data onshore due to compliance concerns. The
project charter will provide a clear path or vision for the project, how it
benefits Merrilton and how the MSP team and the Merrilton IT team will
be working together to complete the project including ground rules.

2. Develop a project charter for the cloud data migration project in the
scenario.

, Merrilton Robotics Project Charter
Project No.: 8675309 Date Charted: 8/10/2024
Merrilton Robotics Data Migration
Problem Statement Goal Statement
As it stands today, Merrilton’s Data Center is housed at the
company’s facility in Houston, TX. The current capacity of
the infrastructure cannot be increased. The IT department
Our goal for this project is to increase infrastructure capacity
does not have the required expertise, resources or
to allow the company to continue to grow.
capacities to properly address the regulatory mandates or
respond to cyber security threats or internal auditing
requirements.
Project Leader Project Approach
Melissa Rosario Traditional (predictive) methodology
Project Team Risks, Constraints & Assumptions
Name Role
John Smith Project Manager Risks
Very tight 6 month timeline to complete migration and ensure proper
Sarah Jones IT Manager testing and decommision of existing data center infrastructure.
Potential for not making deadline.
David Tooey Quality Assurance Constraints
All migrations must be done during maintenance windows and done
department by department. Each migration must adhere to all
security and government regulations throughout the entirty of the
Kent Scandrett Risk Management
project with no loss of data, corruption or security breaches.
Maintenance windows only occur once to two times a week for a 4
hour timeframe.
Gina Rogers Security Consultant Assumptions
Merrilton is assuming that the MSP vendor selected is able to stay
within budget and complete the migration with the given risks and
constraints. In addition, there is the assumption that the MSP has the
Michelle Espadas Chief Engineer
necessary knowledge that the Merrilton IT team doesn't currently
have for the process and maintenance of the new cloud
infrastructure.
Scope Deliverables
As Merrilton Robotics continues to grow, so will the need for data
Increase in storage capacity
storage, maintenance and retrieval.
The use of a third-party Managed Service Provider (MSP) will allow Ease of information access
Merrilton to abide by government regulations, allow for future Governement regulations followed
growth and have the technical knowledge the team currently doesn’t Security standards met
have access to today.


Start Date Estimate Completion Date
10/1/2024 4/1/2025

Milestones 1 2 3 4 5
Determine all
Breakdown Migrate each
infrastructure
Description: components per department to the Testing Complete Migration
components to be
department cloud
moved
Date: 10/1/2024 11/1/2024 1/1/2025 3/1/2025 4/1/2025




Signatures - The signatures of the people below document approval of the formal Project Charter
Signature Date
Project leader: Melissa Rosario

Sponsor: Charlie Reifsteck

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
melissarosario1 Western Governor\'s University
View profile
Follow You need to be logged in order to follow users or courses
Sold
118
Member since
1 year
Number of followers
0
Documents
32
Last sold
2 days ago

3.7

3 reviews

5
0
4
2
3
1
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions