Cost Estimate Merrilton Robotics Data Migration
Timeframe to Complete
Cost Type Task Details (Hours)
Governance
Indirect Establish all government regulations 100
Indirect Ongoing governance meetings 80
Budgeting
Indirect Budget preparation 120
Indirect Presentation, MSP selection, revisions 120
Cloud MSP Data Center
Indirect Location Selection 50
Indirect Administrative Expenses 80
Indirect Contract negotiation 50
Migration Planning
Indirect Cost for creation of move groups 75
Direct Data Backup and Recovery 100
Physical Migration
Indirect Downtime for Migration 10
Direct Dismantelling costs 50
Labor
Direct Cloud vendor costs 50
Direct Dependency mapping costs 50
Post-Migration & Lifecycle
Indirect Monitoring and Maintenance 720
Indirect Personnel training 40
Total Cost
Timeframe to Complete
Cost Type Task Details (Hours)
Governance
Indirect Establish all government regulations 100
Indirect Ongoing governance meetings 80
Budgeting
Indirect Budget preparation 120
Indirect Presentation, MSP selection, revisions 120
Cloud MSP Data Center
Indirect Location Selection 50
Indirect Administrative Expenses 80
Indirect Contract negotiation 50
Migration Planning
Indirect Cost for creation of move groups 75
Direct Data Backup and Recovery 100
Physical Migration
Indirect Downtime for Migration 10
Direct Dismantelling costs 50
Labor
Direct Cloud vendor costs 50
Direct Dependency mapping costs 50
Post-Migration & Lifecycle
Indirect Monitoring and Maintenance 720
Indirect Personnel training 40
Total Cost