CEE 4100 Exam 1 Questions and Correct Solutions
CEE 4100 Exam 1 Questions and Correct Solutions Activity Labor Cost - CORRECT ANSWER-duration x hourly crew labor cost Advertisement for construction - CORRECT ANSWER-request for eligibility to bid - right to reject bids Architect/Engineer - CORRECT ANSWER-•professional that designs project. Usually direct employee of owner by contract Bid Bond - CORRECT ANSWER-Ensures bidder stays with the project Bid Solicitation or Advertisement for Bid - CORRECT ANSWER-contains information regarding bidding documents for public projects BIDDING DOCUMENTS VS. CONTRACT DOCUMENTS - CORRECT ANSWER-Both. agreement, bid form, addenda, drawings, general/supplementary conditions, technical specs Bid docs: notice/invitation to bidders, instruction to bidder, bid bond, performance bond, payment bond Contract docs: modifications business organization - CORRECT ANSWER-I. start of business (fundamental purpose, scope, action plan) 2. design organizational structure (authority, responsibility/ delegation) Civil engineering Specialties - CORRECT ANSWER-ENVIRONMENTAL AND WATER RESOURCES GEOTECHNICAL SYSTEMS STRUCTURAL SYSTEMS
Written for
- Institution
- CEE 4100
- Course
- CEE 4100
Document information
- Uploaded on
- September 29, 2024
- Number of pages
- 9
- Written in
- 2024/2025
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
cee 4100 exam 1 questions and correct solutions
-
correct solutions activity labor cost
Also available in package deal