1. UDC was required at time of installation for all sys- January 1, 2000
tems installed after?
2. July 1, 2005, service techs shall possess or work ICC UST Service
under someone who has a current certification indi- Technician Exam
cating he or she has passed the?
3. ICC cert must be renewed every? 24 months
4. Service techs must possess or be employed by a The individual has
person who has the appropriate contractor's license a tank testing li-
unless? cense
5. Service tech is defined by any individual who? Tests UST moni-
toring equipment,
trouble shoots
UST systems,
and/or installs
UST monitoring
equipment.
6. If the manufacturer training no longer exist, the local Approve compara-
agency may? ble alternate train-
ing .
7. UST includes? Tank and connect-
ed piping
8. What is considered a UST? A petroleum stor-
age tank.
9. What UST system meets the requirements for sec- Doubled wall
ondary containment? tanks
10. According to title 23; the following piping compo- Pressured product
nents if installed after July 1, 1987 must have sec- piping
ondary containment.
11. Considered "pipe" on tanks installed after July 1, Pressured product
2003. piping and below
, ICC California UST Service Technician
ground vapor re-
covery.
12. Under dispenser containment (UDC) was required for December 31,
all existing UST systems by 2003
13. System for exchanging gas vapors in a storage tank Stage 1 vapor re-
and product in a fuel delivery truck covery
14. An approved method for non-visual monitoring for Statistical Invento-
existing UST systems. ry Reconciliation
(SIR)
15. ATG must be capable for detecting a release of? 0.2 gallons per
hour
16. What is no longer an approved method for non-visual Manual inventory
monitoring on existing UST systems? reconciliation.
17. Automatic line leak detectors installed on under- 3 gallons per hour
ground piping with secondary containment shall be at 10 psi
capable of detecting a leak of ?
18. How often should ATG be programmed to test the At least monthly
tank?
19. According to PEI RP 300, a combustible gas can be Detect vapor leaks
used to? in a vapor recov-
ery system.
20. According to PEI RP 300, a written scope of work for Construction
vapor recovery installation should include? plans
21. Positive shut off overfill protection device must stop 95% full
the flow of fuel when the tank is no more then?
22. According to Executive Order (EO) VR 201-A , what Depended filter
could cause a nozzle shut off mechanism or malfunc- seal damage
tion?
, ICC California UST Service Technician
23. According to VR 201-A, breakaway reconnection Logged in GDF
must be? log
24. According to PEI RP 300 what is an INCORRECT Sketching a dia-
method of documenting piping location? gram on the inside
cover of vapor re-
covery equipment
manual
25. According to PEI RP 300 as built drawing or pictures maintained as
of the underground pipping and other components long as UST is in
shall be_________. service.
26. According to EO VR 101-E maintenance records are Name and Desig-
required to include what? nated UST Opera-
tor.
27. The Phil-Tite EVR Phase 1 system require that vapor Used with no more
vent pipes at any UST system be than 3 p/v valves
28. According to EO VR 2010 after installing a new spout Nozzle dispensing
assembly in the Healy 900 nozzle the following test shut off test
must be conducted?
29. According to Healy EO VR 201-A a vapor recovery Gasoline dispens-
record is to be maintained by? ing facility opera-
tor(GDF)
30. An enhanced leak detection test is required within 1000 feet
how many feet of a public drinking well?
31. What are the components of the Fire Triangle? Fuel, Heat/Ignition
Source, Oxygen
32. If equipped with an over fill alarm, it must be located? So it can be seen
or heard from the
delivery location.
33. Automatic Tank
Gauge, Liquid