CLC 222 Module 5 Exam: Contract Monitoring - Documentation & Handling Issues
2022
• The Contracting Officer's Representative is responsible for safeguarding all proprietary data.
o Correct: True
• The COR should only use formal communication when working with a contractor.
o Correct: False
• The Contracting Officer's Representative's normal monitoring activities should shed light
on warning signs of contractor problems, such as a failure to meet performance deadlines.
o Correct: True
• In remedy situations, the Contracting Officer's Representative's oversight duties and
documented files are key to determining the course of action for the government to take.
The COR contributes by:
o Correct: All of the answers are correct
• The COR may release information without consulting with the Contracting Officer or
Legal Counsel.
o Correct: False
2022
• The Contracting Officer's Representative is responsible for safeguarding all proprietary data.
o Correct: True
• The COR should only use formal communication when working with a contractor.
o Correct: False
• The Contracting Officer's Representative's normal monitoring activities should shed light
on warning signs of contractor problems, such as a failure to meet performance deadlines.
o Correct: True
• In remedy situations, the Contracting Officer's Representative's oversight duties and
documented files are key to determining the course of action for the government to take.
The COR contributes by:
o Correct: All of the answers are correct
• The COR may release information without consulting with the Contracting Officer or
Legal Counsel.
o Correct: False