Most Recent Exam 2026|2027 Actual Complete Real Exam Questions
And Correct Answers (Verified Answers) Already Graded A+ |
Guaranteed Success!! Newest Exam | Just Released!!
Retainage standard percentage in Florida public/private projects -
ANSWER-Typically 10% reduced to 5% at 50% project completion in
many standard contracts.
Punch list creation -ANSWER-Compiled near substantial completion,
noting incomplete or defective work to be corrected.
Substantial completion definition -ANSWER-The stage when the work is
sufficiently complete in accordance with contract documents so the
owner can occupy it.
Builder's risk insurance -ANSWER-Property insurance that covers
buildings under construction against loss or damage.
General liability insurance -ANSWER-Protects contractor against third-
party claims for bodily injury, property damage, and personal injury.
Workers' compensation insurance -ANSWER-Mandatory insurance
providing wage replacement and medical benefits to employees injured
on the job.
,Indemnification clause -ANSWER-Contractual provision shifting liability
and risk from one party to another.
Liquidated damages -ANSWER-Predetermined damages specified in the
contract for failure to complete work by the completion date.
Critical path method (CPM) -ANSWER-Project management technique
identifying the longest sequence of dependent activities and shortest
time to complete project.
Float (or slack) in scheduling -ANSWER-The amount of time an activity
can be delayed without delaying the project finish date.
RFI (Request for Information) -ANSWER-Formal document used to
clarify ambiguities or missing details in contract documents.
Submittal process -ANSWER-Review procedure for shop drawings,
product data, and samples prior to equipment or material
procurement.
Mechanic's lien waiver -ANSWER-Legal document relinquishing the
right to file a lien against property upon receipt of payment.
Well-blasted rock has a swell percentage of:
, (Principles and Practices of Commercial Construction --> Earthwork) -
ANSWER-20%
Lifelines in areas subjected to cutting or abrasion shall be a minimum of
______ inch wire core manila rope
(OSHA) -ANSWER-7/8
All excavations made in Type B soil 20 feet or less in depth which have
vertically sided lower portions shall be shielded or supported to a
height _____ inches above the top of the vertical side
(OSHA) -ANSWER-At least 18 inches
The calculated fire-resistance rating for a 3.8 inch thick sand and light
weight aggregate precast concrete wall shall be _______ hour(s).
(Florida Building Code --> Calculated Fire Resistance) -ANSWER-2 hours
Welded splices are almost always necessary in_______.
(Reinforcing Bars --> Welding) -ANSWER-Precast Concrete Construction
6. The OSHA area office has a maximum of ____ days to assess the
penalty for failure to abate a violation.
(Florida Contractors Manual --> Categories of Violations) -ANSWER-30
Days