Contract Administration
Examination Exam
,18574 QUESTIONS
Question 1
For a joint review of Bonds and Insurance and RFI Workflow Management, which
scope avoids leaving either focus out?
A. Reviewing and verifying performance bonds, payment bonds, builder's risk insurance, and
general liability policies; Tracking origin, formulation quality, routing logic, and timely
response thresholds
B. Reviewing and verifying performance bonds, payment bonds, builder's risk insurance, and
general liability policies; Establishing administrative procedures, communication protocols,
chain of command, and reporting standards
C. Tracking origin, formulation quality, routing logic, and timely response thresholds;
Establishing administrative procedures, communication protocols, chain of command, and
reporting standards
D. Establishing administrative procedures, communication protocols, chain of command, and
reporting standards; Reviewing preliminary baseline schedules, safety plans, quality control
programs, and mobilization layouts
Correct Answer: A
Full Explanation:
Reviewing and verifying performance bonds, payment bonds, builder's risk insurance, and general
liability policies is associated with Bonds and Insurance, rather than the specific focus of RFI Workflow
Management. RFI Workflow Management addresses tracking origin, formulation quality, routing logic,
and timely response thresholds. The other entries keep each concern with its own technical area.
Question 2
Which bundle of concerns is most directly relevant to Compensation
Arrangements?
A. Lump sum (fixed price); Cost-Plus-Fee (with or without Guaranteed Maximum Price - GMP);
unit price contracts
B. Lump sum (fixed price); Cost-Plus-Fee (with or without Guaranteed Maximum Price - GMP);
facilitating contract execution and notice to proceed (NTP)
C. Lump sum (fixed price); Cost-Plus-Fee (with or without Guaranteed Maximum Price - GMP);
debriefing unsuccessful bidders
D. Lump sum (fixed price); Cost-Plus-Fee (with or without Guaranteed Maximum Price - GMP);
Drafting
Correct Answer: A
Full Explanation:
The coherent group is Lump sum (fixed price); Cost-Plus-Fee (with or without Guaranteed Maximum
Price - GMP); unit price contracts. These concerns belong together within Compensation
Arrangements. Each other group replaces one relevant concern with an item from a different focus.
2
,18574 QUESTIONS
Question 3
Which entry does not fit the specific grouping used for Issuance of Bidding
Documents?
A. Establishing criteria
B. Managing distribution
C. deposit procedures
D. plan holders lists
Correct Answer: A
Full Explanation:
Establishing criteria is associated with Pre-Qualification of Contractors. In contrast, Managing
distribution; plan holders lists; deposit procedures belong within the specific focus of Issuance of
Bidding Documents.
Question 4
An assessment of Pre-Qualification of Contractors includes Establishing criteria;
bonding capacity; evaluating financial stability. Which companion concern should
also be considered?
A. Public vs. private opening procedures
B. deposit procedures
C. technical competence
D. facilitating contract execution and notice to proceed (NTP)
Correct Answer: C
Full Explanation:
Pre-Qualification of Contractors brings together Establishing criteria; evaluating financial stability;
bonding capacity; technical competence; past performance. technical competence belongs with the
concerns already given; the alternatives shift attention to different subjects.
Question 5
A review of The Punch List has reached Generating; managing; completing
outstanding or deficient items. Which further concern belongs with it?
A. record drawings
B. Collecting as-built drawings
C. transfer of utility responsibilities
D. categorizing
Correct Answer: D
Full Explanation:
The Punch List brings together Generating; managing; categorizing; completing outstanding or
deficient items. categorizing belongs with the concerns already given; the alternatives shift attention
to different subjects.
3
, 18574 QUESTIONS
Question 6
When checking the boundary between Bid Opening Protocols and The Review
Workflow, which entry should be revised?
A. Bid Opening Protocols: Role of the Contractor, CM, and Design Professional in routing, logging,
reviewing timeframes, and returning submittals
B. Pricing and Estimating Changes: Evaluating unit prices, lump-sum proposals, and
time-and-material (T&M) tickets
C. Delivery Method Impact on Administration: Design-Bid-Build (DBB), Construction Manager at
Risk (CMAR/CMGC), Design-Build (DB), and Multi-Prime contracting structures
D. Training and O&M Manuals: Managing delivery, review, and acceptance of operation and
maintenance manuals and owner-operator training sessions
Correct Answer: A
Full Explanation:
Role of the Contractor, CM, and Design Professional in routing, logging, reviewing timeframes, and
returning submittals is associated with The Review Workflow, rather than the specific focus of Bid
Opening Protocols. Bid Opening Protocols addresses public vs. private opening procedures, reading of
bids, and recording documentation. The other entries keep each concern with its own technical area.
Question 7
Which proposed link confuses the concerns of Addenda Management with
Standard Industry Forms of Agreement?
A. The Review Workflow: Role of the Contractor, CM, and Design Professional in routing, logging,
reviewing timeframes, and returning submittals
B. Schedule of Values Evaluation: Reviewing, negotiating, and approving the contractor's initial
breakdown of contract sum
C. Addenda Management: Overview and comparison of standard contract forms (e.g., CMAA,
AIA, ConsensusDocs, EJCDC, Federal FAR)
D. Distinction Between Clarifications and Changes: Identifying RFIs that seek interpretation of
existing contract documents versus those implying scope adjustments or changes
Correct Answer: C
Full Explanation:
Overview and comparison of standard contract forms (e.g., CMAA, AIA, ConsensusDocs, EJCDC,
Federal FAR) is associated with Standard Industry Forms of Agreement, rather than the specific focus
of Addenda Management. Addenda Management addresses drafting, issuing, and tracking
clarifications, modifications, and question-and-answer responses during the bidding window. The
other entries keep each concern with its own technical area.