A+ VERIFIED
Oregon Plumbing Inspector Certification Exam Practice Questions
And Correct Answers (Verified Answers) Plus Rationale Q&A Instant
Download Pdf. 30 Questions
Clinical | Rationale-Driven - Pass Guaranteed - A+ Graded
30 1 30
QUESTIONS SECTIONS RATIONALES
WHAT THIS COVERS
01 Plumbing Inspection and Code Compliance
02 Based on the 2021 Uniform Plumbing Code with Oregon amendments
03 Drainage requirements
04 Water supply
05 Water heaters
06 Backflow prevention
ABOUT THIS ASSESSMENT
This certification exam assesses mastery of the 2023 Oregon Plumbing Specialty Code (OPSC), based on the 2021 Uniform
Plumbing Code with Oregon amendments, and the administrative rules governing plumbing inspections in Oregon. It covers code
administration, fixture and drainage requirements, water supply, venting, traps, water heaters, backflow prevention, fuel gas piping,
and inspector enforcement duties.
, EXAMINATION QUESTIONS
SECTION 1 - Plumbing Inspection and Code Compliance (Questions 1 to 30)
1. For a 3-inch horizontal storm drain receiving 120 gpm, what is the minimum slope required by OPSC 2023 Table
1106.2?
A. 1/8 inch per foot
B. 1/4 inch per foot
C. 1/16 inch per foot
D. 1/2 inch per foot
Answer: A [Concept: Plumbing Inspection and Code Compliance]
Rationale: OPSC 2023 Table 1106.2 specifies that a 3-inch horizontal storm drain with a capacity of 120 gpm requires a minimum
slope of 1/8 inch per foot. A 1/4 inch per foot slope is required for smaller pipes or lower flows, 1/16 inch per foot is not permitted for
storm drains, and 1/2 inch per foot is excessive and not the minimum. Thus, 1/8 inch per foot is correct.
2. A plumbing inspector discovers an unpermitted water heater replacement during a final inspection. Under ORS
455.450, what is the most appropriate enforcement action?
A. Issue a stop-work order and require a permit application
B. Approve the installation if it meets code
C. Refer the matter to the contractor's licensing board
D. Assess a civil penalty without a permit
Answer: A [Concept: Plumbing Inspection and Code Compliance]
Rationale: ORS 455.450 authorizes the building official to issue a stop-work order for work conducted without a permit and require
the responsible party to obtain a permit. Approval without a permit is not permitted, referral to a licensing board is secondary, and
civil penalties are typically assessed after due process, not as the first action. The immediate action is to stop work and require
permitting.
3. A vent stack serving a 3-inch drain must extend how far above the roof?
A. 6 inches
B. 12 inches
C. 18 inches
D. 24 inches
Answer: A [Concept: Plumbing Inspection and Code Compliance]
Rationale: OPSC Section 906.7 specifies that vent extensions through the roof shall extend at least 6 inches above the roof. The
12-inch, 18-inch, and 24-inch options are incorrect; some local codes may require more, but OPSC minimum is 6 inches.
4. Which of the following is the correct minimum size for a building sewer serving a 4-inch building drain with a 1/4
inch per foot slope?
A. 3 inches
B. 4 inches
C. 6 inches
D. 2 inches
Answer: B [Concept: Plumbing Inspection and Code Compliance]
Rationale: OPSC 2023 Section 703.1 requires the building sewer to be at least the same size as the building drain it serves. A 4-inch
building drain therefore requires a minimum 4-inch building sewer. Smaller sizes (3-inch, 2-inch) are not permitted, and 6-inch is
larger than necessary. Thus, 4 inches is correct.
Page 2 | Oregon Plumbing Inspector Certification Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationale Q&A Instant