1. A 4.8kV distribution feeder is carrying 250A per phase at 0.90 power factor
lagging. What is the approximate three-phase apparent power?
A. 1,732 kVA
B. 2,078 kVA
C. 1,870 kVA
D. 2,400 kVA
Rationale: Apparent power S = sqrt(3) x V_LL x I. S = 1.732 x 4.8kV x 250A
= 2,078.4 kVA. Power factor affects real and reactive power, not apparent
power, which is why option C using P=S x pf is incorrect.
2. A Trouble Dispatcher receives simultaneous reports: wires down with arc
near school, life-support customer without power, and a single customer
out due to tripped main. Under LADWP emergency priority, what is the
correct dispatch order?
A. Life-support, wires down, single customer out
B. Single customer out, life-support, wires down
C. Life-support, single customer out, wires down
D. Wires down with arc near school, life-support customer, single
customer out
Rationale: Public safety hazards always take absolute priority per NESC
and LADWP safety rules. Downed energized conductors near a school
create imminent electrocution and public hazard risk and must be made
safe first, followed by life-support/medical baseline, then routine
individual outages.
,3. On a 34.5kV to 4.8kV delta-wye substation transformer, what is the primary
purpose of the wye-grounded secondary?
A. To provide a neutral for single-phase loads and a ground source for fault
detection
B. To increase fault current on the primary
C. To eliminate the need for lightning arresters
D. To balance the delta primary currents
Rationale: A wye-grounded secondary provides a neutral point for
277/480V or single-phase 2.4kV line-to-neutral services, allows ground
fault current to return, and enables ground relay detection. A delta
secondary cannot provide a stable neutral or effective ground fault
detection.
4. A customer reports lights flickering across entire neighborhood. SCADA
shows momentary operations of the feeder recloser at Receiving Station.
What is the most likely cause?
A. Loose service neutral at one residence
B. Defective customer main breaker
C. Transient fault on overhead feeder such as branch contact or lightning
D. Failed underground transformer secondary
Rationale: A feeder-wide momentary flicker correlated with a recloser
operation indicates a transient fault upstream affecting all customers on
that feeder. A loose service neutral would affect only one service, and a
failed secondary transformer would cause a sustained outage in a small
pocket, not a system-wide momentary.
5. What is the correct sequence for de-energizing a 4.8kV overhead line
section for crew protection?
A. Install grounds, open disconnects, tag open
B. Open load-breaking device, open visible disconnects, tag, test for
voltage, install protective grounds
C. Install grounds, test for voltage, open disconnects
D. Open disconnects, install grounds, test for voltage
Rationale: The OSHA and LADWP switching sequence requires breaking
, load first with a rated device, then establishing visible open, then tagging,
then verifying de-energization with approved tester, then installing
grounds on both sides of work zone to protect against backfeed and
induced voltage.
6. According to NESC, what is the minimum approach distance for a qualified
worker to exposed energized parts at 4.8kV phase-to-phase without
specialized live-line tools?
A. 2 feet 1 inch
B. 1 foot 0 inch
C. 3 feet 0 inch
D. 10 feet 0 inch
Rationale: NESC Table 441-1 specifies 2 ft 1 in for 0-50kV range for
qualified employees in AC systems. This is for qualified electrical workers;
unqualified public and equipment require 10 ft clearance which is often
confused with this value.
7. In the Outage Management System OMS, a cluster of 80 no-light calls map
to the same 4.8kV 3-phase mainline fuse downstream of a recloser that
shows locked out. What should the Dispatcher infer?
A. Individual service problems at 80 homes
B. Transmission loss at Receiving Station
C. SCADA communication failure
D. Blown 3-phase mainline fuse or locked out recloser has de-energized
the lateral/feeder section
Rationale: Spatial clustering of outages downstream of a single protective
device that is open/locked out indicates loss of that feeder section, not 80
coincidental individual troubles. The OMS grouping function is designed to
identify common device failure versus scattered singletons.
8. Which device is designed to automatically restore service after a temporary
fault clears?
A. Automatic circuit recloser
B. Expulsion fuse cutout
, C. Current-limiting power fuse
D. Load-break disconnect
Rationale: A recloser is programmed for an operating sequence e.g., 2
fast, 2 delayed operations that tests if fault is temporary and re-energizes
if cleared. Fuses are one-shot sacrificial devices that must be replaced
after operation.
9. A line crew reports a pole is on fire at the base but primary remains
energized. What is the correct Dispatcher action?
A. Advise crew to extinguish with water
B. Declare imminent pole failure hazard, clear area, expedite de-
energization and fire department response, reroute if possible
C. Ignore as non-electrical issue
D. Tell crew to climb and cut primary
Rationale: A burning pole compromises structural integrity and can cause
phase-to-phase or phase-to-ground faults and pole collapse. Water
conducts, crew cannot climb. Correct action is to treat as emergency
public safety hazard, de-energize, coordinate with LAFD, and keep public
clear.
10.What does SCADA acronym stand for in LADWP distribution operations?
A. Supervisory Control and Data Acquisition
B. System Control and Distribution Automation
C. Safety Control and Dispatch Advisory
D. Substation Control and Data Array
Rationale: SCADA is industry standard Supervisory Control and Data
Acquisition system that provides remote monitoring of substation
breakers, feeder loading, voltage, and remote control of switching devices
to Dispatchers.
11.Two adjacent underground residential distribution transformers are
overloaded at 140 percent. Load transfer via secondary tie is not possible.
What switching action best alleviates overload without causing an outage?
A. Open secondary main to shed load
Examination Questions And Correct
Answers (Verified Answers) Plus Rationales
2026 Q&A | Instant Download Pdf
1. A 4.8kV distribution feeder is carrying 250A per phase at 0.90 power factor
lagging. What is the approximate three-phase apparent power?
A. 1,732 kVA
B. 2,078 kVA
C. 1,870 kVA
D. 2,400 kVA
Rationale: Apparent power S = sqrt(3) x V_LL x I. S = 1.732 x 4.8kV x 250A
= 2,078.4 kVA. Power factor affects real and reactive power, not apparent
power, which is why option C using P=S x pf is incorrect.
2. A Trouble Dispatcher receives simultaneous reports: wires down with arc
near school, life-support customer without power, and a single customer
out due to tripped main. Under LADWP emergency priority, what is the
correct dispatch order?
A. Life-support, wires down, single customer out
B. Single customer out, life-support, wires down
C. Life-support, single customer out, wires down
D. Wires down with arc near school, life-support customer, single
customer out
Rationale: Public safety hazards always take absolute priority per NESC
and LADWP safety rules. Downed energized conductors near a school
create imminent electrocution and public hazard risk and must be made
safe first, followed by life-support/medical baseline, then routine
individual outages.
,3. On a 34.5kV to 4.8kV delta-wye substation transformer, what is the primary
purpose of the wye-grounded secondary?
A. To provide a neutral for single-phase loads and a ground source for fault
detection
B. To increase fault current on the primary
C. To eliminate the need for lightning arresters
D. To balance the delta primary currents
Rationale: A wye-grounded secondary provides a neutral point for
277/480V or single-phase 2.4kV line-to-neutral services, allows ground
fault current to return, and enables ground relay detection. A delta
secondary cannot provide a stable neutral or effective ground fault
detection.
4. A customer reports lights flickering across entire neighborhood. SCADA
shows momentary operations of the feeder recloser at Receiving Station.
What is the most likely cause?
A. Loose service neutral at one residence
B. Defective customer main breaker
C. Transient fault on overhead feeder such as branch contact or lightning
D. Failed underground transformer secondary
Rationale: A feeder-wide momentary flicker correlated with a recloser
operation indicates a transient fault upstream affecting all customers on
that feeder. A loose service neutral would affect only one service, and a
failed secondary transformer would cause a sustained outage in a small
pocket, not a system-wide momentary.
5. What is the correct sequence for de-energizing a 4.8kV overhead line
section for crew protection?
A. Install grounds, open disconnects, tag open
B. Open load-breaking device, open visible disconnects, tag, test for
voltage, install protective grounds
C. Install grounds, test for voltage, open disconnects
D. Open disconnects, install grounds, test for voltage
Rationale: The OSHA and LADWP switching sequence requires breaking
, load first with a rated device, then establishing visible open, then tagging,
then verifying de-energization with approved tester, then installing
grounds on both sides of work zone to protect against backfeed and
induced voltage.
6. According to NESC, what is the minimum approach distance for a qualified
worker to exposed energized parts at 4.8kV phase-to-phase without
specialized live-line tools?
A. 2 feet 1 inch
B. 1 foot 0 inch
C. 3 feet 0 inch
D. 10 feet 0 inch
Rationale: NESC Table 441-1 specifies 2 ft 1 in for 0-50kV range for
qualified employees in AC systems. This is for qualified electrical workers;
unqualified public and equipment require 10 ft clearance which is often
confused with this value.
7. In the Outage Management System OMS, a cluster of 80 no-light calls map
to the same 4.8kV 3-phase mainline fuse downstream of a recloser that
shows locked out. What should the Dispatcher infer?
A. Individual service problems at 80 homes
B. Transmission loss at Receiving Station
C. SCADA communication failure
D. Blown 3-phase mainline fuse or locked out recloser has de-energized
the lateral/feeder section
Rationale: Spatial clustering of outages downstream of a single protective
device that is open/locked out indicates loss of that feeder section, not 80
coincidental individual troubles. The OMS grouping function is designed to
identify common device failure versus scattered singletons.
8. Which device is designed to automatically restore service after a temporary
fault clears?
A. Automatic circuit recloser
B. Expulsion fuse cutout
, C. Current-limiting power fuse
D. Load-break disconnect
Rationale: A recloser is programmed for an operating sequence e.g., 2
fast, 2 delayed operations that tests if fault is temporary and re-energizes
if cleared. Fuses are one-shot sacrificial devices that must be replaced
after operation.
9. A line crew reports a pole is on fire at the base but primary remains
energized. What is the correct Dispatcher action?
A. Advise crew to extinguish with water
B. Declare imminent pole failure hazard, clear area, expedite de-
energization and fire department response, reroute if possible
C. Ignore as non-electrical issue
D. Tell crew to climb and cut primary
Rationale: A burning pole compromises structural integrity and can cause
phase-to-phase or phase-to-ground faults and pole collapse. Water
conducts, crew cannot climb. Correct action is to treat as emergency
public safety hazard, de-energize, coordinate with LAFD, and keep public
clear.
10.What does SCADA acronym stand for in LADWP distribution operations?
A. Supervisory Control and Data Acquisition
B. System Control and Distribution Automation
C. Safety Control and Dispatch Advisory
D. Substation Control and Data Array
Rationale: SCADA is industry standard Supervisory Control and Data
Acquisition system that provides remote monitoring of substation
breakers, feeder loading, voltage, and remote control of switching devices
to Dispatchers.
11.Two adjacent underground residential distribution transformers are
overloaded at 140 percent. Load transfer via secondary tie is not possible.
What switching action best alleviates overload without causing an outage?
A. Open secondary main to shed load