Question:
1. Administered by the US environmental protection agency (EPA) Created the NPDES
Answer:
1972 clean water act
Question:
2. Amendment to CWA CALLED WATER QUALITY ACT
Answer:
1987
Question:
3. South Carolina is NPDES delegated state.
Answer:
NPDES in south carolina
Question:
4. SCDHEC
Answer:
NPDES regulations are administered by
Question:
5. stormwater discharges from construction sites
Answer:
CGP authorizes
Question:
6. land disturbing activities greater than or equal to 1 acre
-land disturbance less than 1 ac within 1/2 miles of water body in SC costal zone
Answer:
Who must obtain NPDES coverage
Question:
7. operator-person or company for a particular discharge
Answer:
NPDES permits are issued to
Question:
8. -has day to day operational control to ensure compliance with SWPP
-typically the owner or developer
Answer:
primary permittee
Question:
9. submit NOI, Preparation of the C_SWPPP
, Answer:
primary permittee responsibilites
Question:
10. individual lot owner or residential builder that conducts land disturbing activity limited to an
individual lot or group of lots as part of approved LCP of development
Answer:
Secondary permittee
Question:
11. must on Contractor Certification- D-0437
Answer:
contractors
Question:
12. SCDHEC CGP, NOI, NPDES coverage approval letter, Contractor Certifications, Local
Approvals, USACE approvals, Critical area permit(coast)
Answer:
On-Site SWPPP
Question:
13. a copy of signed and certified SWPPP, NOI, and CGP coverage letter from DHEC must be
retained at site or electronically accessible
Answer:
OS_SWPPP
Question:
14. minor modifications made directly in the field,do not need approval by DHEC- additional BMP's,
removal of disturbed areas
Answer:
minor modification to ON-SWPPP
Question:
15. must be made by qualified individual and submitted to DHEC or appropriate delegated entity for
approval
Answer:
major modifications to OS-SWPPP
Question:
16. include a phased stormwater management plan which identifies all BMP's and grading work
conducted during a specific portion of the sites construction sequence. Each phase identified on at
least one separate plan sheet.
Answer:
Phased plan requirement > 5
Question:
17. at least two separate plan phases are required - initial land disturbance phase - stabilization phase
QUESTIONS AND CORRECT ANSWERS
Question:
1. Administered by the US environmental protection agency (EPA) Created the NPDES
Answer:
1972 clean water act
Question:
2. Amendment to CWA CALLED WATER QUALITY ACT
Answer:
1987
Question:
3. South Carolina is NPDES delegated state.
Answer:
NPDES in south carolina
Question:
4. SCDHEC
Answer:
NPDES regulations are administered by
Question:
5. stormwater discharges from construction sites
Answer:
CGP authorizes
Question:
6. land disturbing activities greater than or equal to 1 acre
-land disturbance less than 1 ac within 1/2 miles of water body in SC costal zone
Answer:
Who must obtain NPDES coverage
Question:
7. operator-person or company for a particular discharge
Answer:
NPDES permits are issued to
Question:
8. -has day to day operational control to ensure compliance with SWPP
-typically the owner or developer
Answer:
primary permittee
Question:
9. submit NOI, Preparation of the C_SWPPP
, Answer:
primary permittee responsibilites
Question:
10. individual lot owner or residential builder that conducts land disturbing activity limited to an
individual lot or group of lots as part of approved LCP of development
Answer:
Secondary permittee
Question:
11. must on Contractor Certification- D-0437
Answer:
contractors
Question:
12. SCDHEC CGP, NOI, NPDES coverage approval letter, Contractor Certifications, Local
Approvals, USACE approvals, Critical area permit(coast)
Answer:
On-Site SWPPP
Question:
13. a copy of signed and certified SWPPP, NOI, and CGP coverage letter from DHEC must be
retained at site or electronically accessible
Answer:
OS_SWPPP
Question:
14. minor modifications made directly in the field,do not need approval by DHEC- additional BMP's,
removal of disturbed areas
Answer:
minor modification to ON-SWPPP
Question:
15. must be made by qualified individual and submitted to DHEC or appropriate delegated entity for
approval
Answer:
major modifications to OS-SWPPP
Question:
16. include a phased stormwater management plan which identifies all BMP's and grading work
conducted during a specific portion of the sites construction sequence. Each phase identified on at
least one separate plan sheet.
Answer:
Phased plan requirement > 5
Question:
17. at least two separate plan phases are required - initial land disturbance phase - stabilization phase