EXAMINATION 2026 VERIFIED SOLUTIONS
GRADED A+
⩥ Design PM Tasks. Answer: Review expression of interest for client
Perform a user needs analysis
Perform site surveys and meet with client
Generate preliminary design submittals
Respond to/incorporate client comments
Prepare final bid documents/RFP and engineer's cost estimate
Issue final RFP package to client
Client makes RFP available to potential bidders
⩥ Implementation of TPM Project Flowchart. Answer: Review client
RFP
Perform Site Survey
Organize and Submit Bid Questions
Organize and Submit Final Proposal
Client Awards Contract NTP
Contractor Mobilizes
Project Implementation
,⩥ Project. Answer: Temporary endevour that has a definite beginning
and end, whose end result is the delivery of a product or service. Projects
are governed by limits (constraints).
⩥ Project Constraints. Answer: Time, Cost, Quality, Resources, Risks,
Safety, Technology, Stakeholders, Environment
⩥ Project Stakeholders. Answer: Sponsor
Portfolio Manager
Client
Sellers
Business Partner
Operations Manager
Functional Manager
Project Manager
Program Manager
⩥ Project Team Members. Answer: Manufacturer
Engineer
Government / Regulatory
Supplier
Vendor
Admin/ Clerical
,Supervisor
Other Trades
Consultant
Coworker
Customer
⩥ ICT Professional's Role is Affected By:. Answer: Current & future
technology
Availability of resources
Complex equipment
Advanced tools
Constant refinement of standards
International, National, Regional and Local Codes
Intricate and evolvoing designs
⩥ Phases of a Project. Answer: Design
Bidding
Construction
Post-Construction
⩥ PM Tools. Answer: Program Evaluation Review Technique (PERT)
Gantt - Schedule of activity, bar chart
, Critical Path Management
Earned Value Management
⩥ TPM Steps. Answer: Developing a Plan
Implementing the Plan
Managing/ Tracking the Plan
Closeout the Project
⩥ TPM Knowledge Areas. Answer: Integration
Scope
Time
Cost
Quality
Human Resources
Communications
Risks
Procurement
Stakeholders
⩥ Human Resource Management. Answer: Personnel issues, engaging
the right people to do the job, (trained, equipped, motivated)
Project Safety