Solutions
A continuous monitoring process used to track the variances
between actual performance and planned performance on a
project, specifically concerning cost and time Correct Answers
Cost control
A document that establishes the template for measuring work
progress as it relates to requests for payment Correct Answers
Schedule of Values
A fine issued by some contractors to subcontractors for failure to
clean their working space and remove their waste from the site.
Correct Answers Back Charges
A penalty assessed to the Contractor for each day the projects
extends beyond the necessary completion date. Correct Answers
Liquidated damages
A physical model or small sample of construction to allow the
architect and owner to review the appearance and function of
materials, colors, textures Correct Answers Mockup
A project delivery method in which the owner holds two
separate contracts for design and construction is: Correct
Answers Design-bid-build method
A reference number used to track cost and schedule information
on materials, labor, subcontracts, equipment, overhead, and fees
, throughout the project control process Correct Answers Cost
code
A type of plan that would portable toilet, dumpsters, and on-site
parking areas Correct Answers A site logistics plan
All of the following are functions of Construction Management
except:
A.Financing the project
B.Planning the project
C.Scheduling the project
D.Estimating the project Correct Answers A. Financing the
project
An estimate is a best-guess of the costs of materials, equipment,
and labor to the contractor to do the project and it includes:
A.General overhead items
B.Profit
C.General overhead items and profit
D.None of the above Correct Answers D. None of the above
An onsite safety plan should cover any and all possible safety
problems inherent with the type of construction at that site. This
is part of: Correct Answers Managing Safety
An order from the owner to add features to or subtract features
from the scope of the project resulting in revision to the contract
is known as: Correct Answers A change order
Because of early involvement of the construction entity with the
planning phase, these two project delivery methods are similar: