The 1970's law that set into place the regulation of stormwater is: - (answer)The Clean Water Act
Requirements for managing stormwater activity on a construction site are outlined in the following
regulation: - (answer)NPDES
Which of the following is never an allowable stormwater discharge from a construction site? -
(answer)Discharge from contaminated groundwater
The Notice of termination can filed when: - (answer)All construction activity, inside and outside the
building, is complete and permanent stabilization verified
Relative to stormwater permitting, all of the following must occur before construction starts except: -
(answer)Submit the notice of termination (NOT)
Which erosion control best mgmt practice increases water infiltration, dissipates rainfall energy and
slows overland flow of stormwater - (answer)Vegetation
Of the following factors that influence erosion rates, the one a contractor has the most control over is: -
(answer)Groundcover
Temporary stabilization should be implemented - (answer)Immediately on all disturbed areas that are
likely to or will remain inactive for 14-days or more
The Primary purpose of a construction exit is - (answer)To remove sediment from construction site
vehicles and minimize trackout
Common types of erosion include all of the following except - (answer)Sedimentation
Which of the following is NOT a beneficial use of water? - (answer)Flushing a spill down a storm drain
DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW
VERSION!!
The 1970's law that set into place the regulation of stormwater is: - (answer)The Clean Water Act
Requirements for managing stormwater activity on a construction site are outlined in the following
regulation: - (answer)NPDES
Which of the following is never an allowable stormwater discharge from a construction site? -
(answer)Discharge from contaminated groundwater
The Notice of termination can filed when: - (answer)All construction activity, inside and outside the
building, is complete and permanent stabilization verified
Relative to stormwater permitting, all of the following must occur before construction starts except: -
(answer)Submit the notice of termination (NOT)
Which erosion control best mgmt practice increases water infiltration, dissipates rainfall energy and
slows overland flow of stormwater - (answer)Vegetation
Of the following factors that influence erosion rates, the one a contractor has the most control over is: -
(answer)Groundcover
Temporary stabilization should be implemented - (answer)Immediately on all disturbed areas that are
likely to or will remain inactive for 14-days or more
The Primary purpose of a construction exit is - (answer)To remove sediment from construction site
vehicles and minimize trackout
Common types of erosion include all of the following except - (answer)Sedimentation
Which of the following is NOT a beneficial use of water? - (answer)Flushing a spill down a storm drain