OMIS 352 FINAL EXAM ACTUAL QUESTIONS
WITH CORRECT DETAILED ANSWERS LATEST
UPDATES 2026 (VERIFIED ANSWERS ) ALREADY
GRADED A+
In an AOA network diagram, _____ occur when two or more activities follow a single node.
a. bursts
b. combinations
c. buffers
d. mergers - a. bursts
In project time management, the process of_____ primarily involves checking and managing
changes to the project schedule.
a. developing the schedule
b. estimating activity resources
c. estimating activity durations
d. controlling the schedule - d. controlling the schedule
Which of the following processes in project time management involves identifying the specific
tasks that the project team members and stakeholders must perform to produce the project
deliverables?
a. Sequencing activities
b. Developing the schedule
, c. Estimating activity durations
d. Defining activities - d. Defining activities
In project time management, which of the following processes involve analyzing activity
sequences, activity resource estimates, and activity duration estimates to create the project
schedule?
a. Developing the schedule
b. Planning schedule management
c. Controlling the schedule
d. Defining activities - a. Developing the schedule
Which of the following is a network diagramming technique used primarily to predict total
project duration?
a. Critical path analysis
b. Gantt chart
c. Resource breakdown structure
d. Arrow diagramming method - a. Critical path analysis
After defining project activities, the next step in project time management is developing the
schedule. - False
A backward pass through the network diagram determines the early start and early finish dates
for each activity. - False
A dependency pertains to the sequencing of project activities or tasks. - True
The arrows in a network diagram represent missed milestones in a project. - False
WITH CORRECT DETAILED ANSWERS LATEST
UPDATES 2026 (VERIFIED ANSWERS ) ALREADY
GRADED A+
In an AOA network diagram, _____ occur when two or more activities follow a single node.
a. bursts
b. combinations
c. buffers
d. mergers - a. bursts
In project time management, the process of_____ primarily involves checking and managing
changes to the project schedule.
a. developing the schedule
b. estimating activity resources
c. estimating activity durations
d. controlling the schedule - d. controlling the schedule
Which of the following processes in project time management involves identifying the specific
tasks that the project team members and stakeholders must perform to produce the project
deliverables?
a. Sequencing activities
b. Developing the schedule
, c. Estimating activity durations
d. Defining activities - d. Defining activities
In project time management, which of the following processes involve analyzing activity
sequences, activity resource estimates, and activity duration estimates to create the project
schedule?
a. Developing the schedule
b. Planning schedule management
c. Controlling the schedule
d. Defining activities - a. Developing the schedule
Which of the following is a network diagramming technique used primarily to predict total
project duration?
a. Critical path analysis
b. Gantt chart
c. Resource breakdown structure
d. Arrow diagramming method - a. Critical path analysis
After defining project activities, the next step in project time management is developing the
schedule. - False
A backward pass through the network diagram determines the early start and early finish dates
for each activity. - False
A dependency pertains to the sequencing of project activities or tasks. - True
The arrows in a network diagram represent missed milestones in a project. - False