FINAL EXAM 2026-2027 BANK CURRENTLY TESTING
COMPLETE EXAM QUESTIONS WITH DETAILED
VERIFIED ANSWERS /EXPERT VERIFIED /ALREADY
GRADED A+/BRAND NEW!!
earned value management - ANSWER-evm
earned value management - ANSWER-a widely accepted
method of measuring project performance and progress of
actual cost against the budgeted / Plan cost
earned value - ANSWER-Ev
,earned value - ANSWER-the total dollar budget of the
work that has been completed
planned value - ANSWER-PV
50-50 rule - ANSWER-when a task is the same 50%
complete as soon as it is started and the task is
considered 100% upon completion
0-100 rule - ANSWER-assign 0% activities that have not
been started and those that are in progress and completed
activities are signed 100%
Earned Value (EV) - ANSWER-the total dollar budget of
the work that has been completed
-measures both schedule and cost performance.
, Earned Value Management (EVM) is - ANSWER-a widely
accepted method of measuring project performance and
progress of actual cost against the budgeted/planned cost`
EVA results allow - ANSWER-the project manager to
communicate performance results to the stakeholders and
make decisions or recommendations for changes if the
results do not align properly with the baseline budget and
schedule.
EVA - ANSWER-measures schedule and cost
performance separately for a specific point in time.