100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

DBIA Test Prep 2026/2027: Complete Guide to Design-Build & Project Delivery Newest version

Rating
-
Sold
-
Pages
10
Grade
A+
Uploaded on
27-11-2025
Written in
2025/2026

A comprehensive study guide for the DBIA (Design-Build Institute of America) certification exam. This document covers all key concepts for 2025/2026, including project delivery systems (Design-Build, CMAR, DBB, IPD), procurement methods (QBS, Best Value), contracting approaches, legal doctrines, insurance, and risk management. Features 109 questions with verified answers for effective exam preparation. 1. Project Delivery System - Answer>>-How team members are organized, establishes when parties engage, determines roles of parties, and determines sequence of design, procurement, and construction (db, cmar, dbb) 2. Procurement Method - Answer>>-how team members are selected (QBS, best value, low price, sole source) 3. Contracting approach - Answer>>-how team members are paid (fp, gmp, cost reimbursement, target price, unit price) 4. Design-Bid-Build (DBB) - Answer>>-linear, sequential process, A/E selected on qualifications, GC selected on low price, design is fully completed without input from GC, A/E acting in owner's interests, with a historically strong bond, process is well-established and understood 5. Construction manager at risk - Answer>>-similar org structure to DBB, construction manager selected by QBS or best value, contractor provides precon services, negotiated gmp contracting approach, open book estimating process, potential to fast track project, construction cost determined before design completed, potential issues over what is reasonably inferable from gmp design documents 6. Design-Build - Answer>>-The owner contracts with one entity (a person or firm) to provide both design and construction services, designer and contractor have a direct contractual relationship, selected by QBS or best value, wide spectrum of contracting approaches and organizational structures, single point responsibility, owner does not manage designer, owner exposure to claims is significantly reduced 7. Engineer procure construct (epc) - Answer>>-similar to design build, in industrial and power generation sectors, systems and performance testing are central to scope, contractor will typically perform engineering with its in-house staff, owner has need for single point responsibility, contracts include plant and process performance guarantees, contract items include performance and schedule liquidated damages and limitations of liability 8. Multiple Prime Contracting - Answer>>-owner contracts with multiple trade contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate the work 9. Integrated Project Delivery (IPD) - Answer>>-multi-party agreement - all parties equal, QBS procurement and target pricing contract approach, private sector use (limited at this time), key: owner's ability to accept risk 10. Public-private partnership (p3) - Answer>>-Instead of government building and maintaining major infrastructure (such as highway, water treatment plant), build and maintenance is outsourced to a private company. Opposed by public sector unions. This is not considered a delivery system but its underlying approaches are delivery systems and typically use DB. Multiple procurement and contracting approaches 11. Shift left - Answer>>-intense efforts to establish scope early in the process; drives early team formation to include key trade subcontractors; can enable big decisions to be made early, affect project outcomes at lowest cost, establish a need for co-location and collaboration, and compress time during concurrent design and construction 12. Traditional design build - Answer>>-typically two-phase best value procurement with lump sum contract; owner defines project requirements and scope of prescriptive work; use of performance-based technical requirements with limited prescriptive specifications 13. Progressive design build - Answer>>-design and price are progressively developed after the design-builder is under contract; final project cost and schedule commitment is not established as part of the selection process; two phases: preliminary services and final design and construction services 14. Criteria documents - Answer>>-describe the end result 15. Bridging documents - Answer>>-prescribes how to achieve the end result 16. Design bid build paradigm - Answer>>-prior to bidding, owner undertakes a process to design the project and all of its details to 100% complete plans and specs. The owner is therefore responsible for success or failure of details of the design, and warrants the sufficiency of design to the contractor. The owner is therefore liable to the contractor for any gaps between plans and specifications and owner's requirements for project performance 17. Design details responsibility - Answer>>-the owner should define its performance requirements and award the contract on the basis of preliminary design; this makes the design-builder responsible for completing the design in accordance with the owner's performance requirements. That also causes the design-builder to warrant the sufficiency of the design to meet the owner's criteria and the sufficiency of the design to subcontractors/suppliers that have no design responsibility 18. Uniformat - Answer>>-subdivides project by functional elements, focuses on systems and assemblies, useful for preliminary information and early design phases, aligns with BIM models and conceptual estimating 19. Master format - Answer>>-subdivides work by results/trades, focuses on building materials, products, and activities, useful for detailed information during final design and construction phases, and aligns with detailed estimating

Show more Read less
Institution
DBIA
Module
DBIA









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
DBIA
Module
DBIA

Document information

Uploaded on
November 27, 2025
Number of pages
10
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

DBIA Test Newest Version 2025/2026 Questions
with Verified Answers
1. Project Delivery System - Answer>>-How team members are organized, establishes
when parties engage, determines roles of parties, and determines sequence of design,
procurement, and construction (db, cmar, dbb)

2. Procurement Method - Answer>>-how team members are selected (QBS, best value, low
price, sole source)

3. Contracting approach - Answer>>-how team members are paid (fp, gmp, cost
reimbursement, target price, unit price)

4. Design-Bid-Build (DBB) - Answer>>-linear, sequential process, A/E selected on
qualifications, GC selected on low price, design is fully completed without input from
GC, A/E acting in owner's interests, with a historically strong bond, process is well-
established and understood

5. Construction manager at risk - Answer>>-similar org structure to DBB, construction
manager selected by QBS or best value, contractor provides precon services, negotiated
gmp contracting approach, open book estimating process, potential to fast track project,
construction cost determined before design completed, potential issues over what is
reasonably inferable from gmp design documents

6. Design-Build - Answer>>-The owner contracts with one entity (a person or firm) to
provide both design and construction services, designer and contractor have a direct
contractual relationship, selected by QBS or best value, wide spectrum of contracting
approaches and organizational structures, single point responsibility, owner does not
manage designer, owner exposure to claims is significantly reduced

7. Engineer procure construct (epc) - Answer>>-similar to design build, in industrial and
power generation sectors, systems and performance testing are central to scope,
contractor will typically perform engineering with its in-house staff, owner has need for
single point responsibility, contracts include plant and process performance guarantees,
contract items include performance and schedule liquidated damages and limitations of
liability

8. Multiple Prime Contracting - Answer>>-owner contracts with multiple trade contractors,
attributes are typically similar to dbb, owner's ability to schedule and coordinate the work

9. Integrated Project Delivery (IPD) - Answer>>-multi-party agreement - all parties equal,
QBS procurement and target pricing contract approach, private sector use (limited at this
time), key: owner's ability to accept risk

, 10. Public-private partnership (p3) - Answer>>-Instead of government building and
maintaining major infrastructure (such as highway, water treatment plant), build and
maintenance is outsourced to a private company. Opposed by public sector unions. This
is not considered a delivery system but its underlying approaches are delivery systems
and typically use DB. Multiple procurement and contracting approaches

11. Shift left - Answer>>-intense efforts to establish scope early in the process; drives early
team formation to include key trade subcontractors; can enable big decisions to be made
early, affect project outcomes at lowest cost, establish a need for co-location and
collaboration, and compress time during concurrent design and construction

12. Traditional design build - Answer>>-typically two-phase best value procurement with
lump sum contract; owner defines project requirements and scope of prescriptive work;
use of performance-based technical requirements with limited prescriptive specifications

13. Progressive design build - Answer>>-design and price are progressively developed after
the design-builder is under contract; final project cost and schedule commitment is not
established as part of the selection process; two phases: preliminary services and final
design and construction services

14. Criteria documents - Answer>>-describe the end result

15. Bridging documents - Answer>>-prescribes how to achieve the end result

16. Design bid build paradigm - Answer>>-prior to bidding, owner undertakes a process to
design the project and all of its details to 100% complete plans and specs. The owner is
therefore responsible for success or failure of details of the design, and warrants the
sufficiency of design to the contractor. The owner is therefore liable to the contractor for
any gaps between plans and specifications and owner's requirements for project
performance

17. Design details responsibility - Answer>>-the owner should define its performance
requirements and award the contract on the basis of preliminary design; this makes the
design-builder responsible for completing the design in accordance with the owner's
performance requirements. That also causes the design-builder to warrant the sufficiency
of the design to meet the owner's criteria and the sufficiency of the design to
subcontractors/suppliers that have no design responsibility

18. Uniformat - Answer>>-subdivides project by functional elements, focuses on systems
and assemblies, useful for preliminary information and early design phases, aligns with
BIM models and conceptual estimating

19. Master format - Answer>>-subdivides work by results/trades, focuses on building
materials, products, and activities, useful for detailed information during final design and
construction phases, and aligns with detailed estimating

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorGeoff NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
Follow You need to be logged in order to follow users or courses
Sold
19
Member since
7 months
Number of followers
0
Documents
248
Last sold
1 week ago
TutorGeoff

Welcome to Tutor Geoff, your go-to source for high-quality test banks and study materials designed to help you excel academically. We offer a comprehensive range of resources including test banks, study guides, solution manuals, and other study materials, all meticulously curated to ensure accuracy and effectiveness. Our affordable, instantly accessible materials are complemented by excellent customer support, making your learning experience seamless and efficient. Trust Tutor Geoff to be your partner in academic success, providing the tools you need to achieve your educational goals.

Read more Read less
4.2

6 reviews

5
4
4
1
3
0
2
0
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions