ACTUAL EXAM QUESTIONS AND
CORRECT ANSWERS LATEST
GUIDE 2025/2026 GRADED A+ .
,1. Based on the guide quantity of 100 CY on a bid document for rock excavation, a contractor bid a unit price of
$20/CY. If the owner's representative determined that the contractor excavated 85 CY of rock during construction, how
much will the contractor get paid?
(a). $2000
(b). $1700
(c). $300
(d). $1800 ✓✓ correct answer (b)
2. Which of the following documents are included in the bid package?
I. Proposal Form
II. Special Conditions
III. Technical Specifications
IV. General Conditions
V. Bid Bond
(a). I, II, and III
(b). II, III, and IV
(c). I, II, IV, and V
(d). I, II, III, and IV ✓✓ correct answer (d)
3. The document requested by the owner as a protection against the risk of the contractor not accepting the job
once awarded the project is
(a). Insurance
(b). Performance Bond
(c). Bid Bond
(d). Payment Bond ✓✓ correct answer (c)
4. Which of the following would not be considered an excusable delay?
(a). Labor Strikes
(b). Review process delays
(c). A hurricane closing a port delaying delivery of materials
(d). Death of a contractor ✓✓ correct answer (b)
, 5. The typically 30-90 days period after the bid opening where the contractor is bound by their bid is called
(a). Acceptance period
(b). Bid period
(c). Anxiety period
(d). Risk period ✓✓ correct answer (a)
6. The procedure that allows a contractor to propose changes to the design with the approval of the designer to
save time and/or money is called
(a). Process Engineering
(b). Value Engineering
(c). Design build engineering
(d). Cost engineering ✓✓ correct answer (b)
7. Which of the following documents determines the zero day of the project for scheduling purposes?
(a). Proposal Form
(b). Formal contract
(c). Notice to bidders
(d). Notice to proceed ✓✓ correct answer (d)
8. The amount held back from the payments to give the contractor an incentive to finish the job on time is called
(a). Retainage
(b). Escrow
(c). Progress Payment
(d). Liquidated damages ✓✓ correct answer (a)
9. Which of the following types of contracts require the contractor to carry the risk of increased costs
(a). Cost + %fee
(b). Cost + fixed fee
(c). Target price with profit sharing
(d). GMP ✓✓ correct answer (d)
10. Which of the following is included in a lump sum bid price?
(a). Direct cost of construction
(b). Indirect costs of construction