100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CONSTRUCTION MANAGEMENT ACTUAL EXAM QUESTIONS AND CORRECT ANSWERS LATEST GUIDE 2025/2026 GRADED A+ .

Rating
-
Sold
-
Pages
20
Grade
A+
Uploaded on
13-10-2025
Written in
2025/2026

1. Based on the guide quantity of 100 CY on a bid document for rock excavation, a contractor bid a unit price of $20/CY. If the owner's representative determined that the contractor excavated 85 CY of rock during construction, how much will the contractor get paid? (a). $2000 (b). $1700 (c). $300 (d). $1800 correct answer (b) 2. Which of the following documents are included in the bid package? I. Proposal Form II. Special Conditions III. Technical Specifications IV.General Conditions V.Bid Bond (a). I, II, and III (b). II, III, and IV (c). I, II, IV, and V (d). I, II, III, and IV correct answer (d) 3. The document requested by the owner as a protection against the risk of the contractor not accepting the job once awarded the project is (a). Insurance (b). Performance Bond (c). Bid Bond (d). Payment Bond correct answer (c) 4. Which of the following would not be considered an excusable delay? (a). Labor Strikes (b). Review process delays (c). A hurricane closing a port delaying delivery of materials (d). Death of a contractor correct answer (b) 3 / 20 5. The typically 30-90 days period after the bid opening where the contractor is bound by their bid is called (a). Acceptance period (b). Bid period (c). Anxiety period (d). Risk period correct answer (a) 6. The procedure that allows a contractor to propose changes to the design with the approval of the designer to save time and/or money is called (a). Process Engineering (b). Value Engineering (c). Design build engineering (d). Cost engineering correct answer (b) 7. Which of the following documents determines the zero day of the project for scheduling purposes? (a). Proposal Form (b). Formal contract (c). Notice to bidders (d). Notice to proceed correct answer (d) 8. The amount held back from the payments to give the contractor an incentive to finish the job on time is called (a). Retainage (b). Escrow (c). Progress Payment (d). Liquidated damages correct answer (a) 9. Which ofthe following types of contractsrequire the contractorto carry the risk of increased costs (a). Cost + %fee (b). Cost + fixed fee (c). Target price with profit sharing (d). GMP correct answer (d) 10. Which of the following is included in a lump sum bid price? (a). Direct cost of construction (b). Indirect costs of construction 4 / 20 (c). change orders (d). Home office overhead correct answer (a),(b),(d) 5 / 20 11. Which of the following are NOT true for design bid build project delivery system? I. Lowest responsible price is used II. Phased construction is possible III. Contractor carries most of risk IV.Designers have access to contractor's expertise (a). I and IV (b). II and IV (c). II and III (d). II, III, and IV correct answer (b). 12. Why may a mobilization payment by the owner decrease the financing cost of a project? (a). Typically the owner's cost of borrowing money is lower compared to the contractor (b). due to increased value of an earlier payment (c). Because of inflation (d). Delayed payments won't have to be paid back. correct answer (a) 13. Which ofthe following delivery methods allow contractor'sinput during the design phase? I. CM @ Risk II. DBB III. DB IV.CM Agency (a). I and III (b).I, II, and IV (c). I, III, and IV (d). II, III, and IV correct answer (c)

Show more Read less
Institution
Module










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Module

Document information

Uploaded on
October 13, 2025
Number of pages
20
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CONSTRUCTION MANAGEMENT
ACTUAL EXAM QUESTIONS AND
CORRECT ANSWERS LATEST
GUIDE 2025/2026 GRADED A+ .






,1. Based on the guide quantity of 100 CY on a bid document for rock excavation, a contractor bid a unit price of
$20/CY. If the owner's representative determined that the contractor excavated 85 CY of rock during construction, how
much will the contractor get paid?
(a). $2000

(b). $1700

(c). $300

(d). $1800 ✓✓ correct answer (b)

2. Which of the following documents are included in the bid package?

I. Proposal Form
II. Special Conditions

III. Technical Specifications

IV. General Conditions
V. Bid Bond
(a). I, II, and III

(b). II, III, and IV

(c). I, II, IV, and V

(d). I, II, III, and IV ✓✓ correct answer (d)

3. The document requested by the owner as a protection against the risk of the contractor not accepting the job
once awarded the project is
(a). Insurance

(b). Performance Bond

(c). Bid Bond

(d). Payment Bond ✓✓ correct answer (c)

4. Which of the following would not be considered an excusable delay?

(a). Labor Strikes
(b). Review process delays

(c). A hurricane closing a port delaying delivery of materials

(d). Death of a contractor ✓✓ correct answer (b)


, 5. The typically 30-90 days period after the bid opening where the contractor is bound by their bid is called
(a). Acceptance period
(b). Bid period

(c). Anxiety period

(d). Risk period ✓✓ correct answer (a)

6. The procedure that allows a contractor to propose changes to the design with the approval of the designer to
save time and/or money is called
(a). Process Engineering

(b). Value Engineering

(c). Design build engineering

(d). Cost engineering ✓✓ correct answer (b)

7. Which of the following documents determines the zero day of the project for scheduling purposes?
(a). Proposal Form

(b). Formal contract

(c). Notice to bidders

(d). Notice to proceed ✓✓ correct answer (d)

8. The amount held back from the payments to give the contractor an incentive to finish the job on time is called
(a). Retainage

(b). Escrow

(c). Progress Payment

(d). Liquidated damages ✓✓ correct answer (a)

9. Which of the following types of contracts require the contractor to carry the risk of increased costs
(a). Cost + %fee

(b). Cost + fixed fee

(c). Target price with profit sharing

(d). GMP ✓✓ correct answer (d)

10. Which of the following is included in a lump sum bid price?

(a). Direct cost of construction

(b). Indirect costs of construction

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
lectdenis Chamberlain College Of Nursing
Follow You need to be logged in order to follow users or courses
Sold
2041
Member since
4 year
Number of followers
1588
Documents
6195
Last sold
5 days ago
online tutor

FOR THE BEST ASSIGNMENTS AND HOMEWORKS ,TO HELP AND TUTORING ALL KIND OF EXAMS

3.7

289 reviews

5
128
4
48
3
47
2
18
1
48

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions